SITE ACCEPTANCE CHECKLIST
(continued)
10. REMARKS/NOTES
11. GENERAL INFORMATION
Site accepted by:
Name:
Title:
Company:
Signature:
Date:
Site approved by:
Name:
Title:
Company:
Signature:
Date:
9.2
Site Acceptance Checklist Notes
The following notes provide important additional information about the Site
Acceptance Checklist.
1 Antenna Mounting
◦
Mounting pole is of sufficient height to clear local obstructions, such as
parapets, window cleaning gantries, and lift housings.
◦
Mounting Pole is of sufficient height, and is safely positioned, so as not to
cause a safety hazard. No person should be able to walk in front of, or look
directly into the path of the microwave radio beam. Where possible, the
pole should be away from the edge of the building.
◦
Mounting pole is secure and perpendicular. A pole that is not
perpendicular may cause problems during antenna alignment.
◦
Mounting pole is grounded as per site specifications. All operators and site
owners have specific requirements regarding the grounding of
installations. As a minimum, typical requirements are such that any metal
structure must be connected to the existing lightning protection ground of
the building. Where it extends beyond the 45 degree cone of protection of
existing lightning conductors, additional lightning protectors should be
installed.