7.0 COMMISSIONING CHECKLIST
7.0 Commissioning Checklist
After installing and programming the system using SpeedCheck Manager software, the following commissioning
verification checklist helps ensure that everything is working as it should be and that your traffic product is ready
to serve the public for many years of reliable and sustained operation.
For All Versions:
All settings are correct using the SpeedCheck Manager software, including slow down options, external
beacon options, calendar-based scheduler, and data collection settings.
“Roll up” sequence occurs and LEDs light upon startup. External output loads such as beacons power up
as expected.
SpeedCheck enclosure is aimed properly in the correct direction toward oncoming traffic lanes.
For Solar Versions:
Before installing battery, confirm it is in a good state of health.
The solar panel is securely mounted with hardware fully tightened.
Ensure there is a green charging status LED showing on the charge controller to confirm solar charging is
taking place.
System has clear sky access and no removal of obstructions is required.
Note the possibility for nearby foliage to eventually shade the solar panel. If so, set a reminder to inspect
later.
Solar panel pointed south (or wherever custom instructions indicate).
Cabinet door is fully closed with an audible “click”.
For AC Versions:
If present, cabinet door is fully closed.
Verify all fuses are intact.
For StreetHub™ remote connectivity versions:
Remote systems are visible in the Glance web interface.