7.1 - Process Site Selection
M2041/5en
SBT-2400 Appendix
59
©BTG 2006
7.1.4
Multiple Bend Piping Installation
If there are multiple bends upstream of the transmitter, then the L
D
must be
equal to L or longer. If not, flow guides must be installed.
Two successive pipe bends can also create as twisting flow that cannot be
straightened, even if the recommended straight sections are used.
Calculation example for pipe with multiple bends
D = 200 mm
Cs = 3.5%, chemical pulp
V = 2.4 m/s
The nomogram shows a relative length (L/D)
7.5. The Mp constant is 1
and the Ic constant is 1.
L
B
= L/D x D x Mp x Ic
L
B
= 7.5 x 200 x 1 x 1 = 1500 mm.
L
A
= 0.5 x L
B
L
A
= 750 mm
L
D
= L
B
or more
L
D
= 1500 mm or more
The recommended length upstream of the transmitter is 2250 mm and the
recommended length downstream of the transmitter is 1125 mm. The
recommended
L
D
value must be 1500 mm or more.
≈
L
B
L
A
L
D
L
B
L
A
L
D
Fig
5 Multiple bends
scenario
Содержание Pulptec SBT-2400
Страница 1: ...USER MANUAL Pulptec BTG Pulp Paper Sensors AB SBT 2400 Static Blade Consistency Transmitter M2041 5en ...
Страница 12: ...1 4 Type Sign Explanation 6 SBT 2400 Product Introduction M2041 5en BTG 2006 ...
Страница 26: ...3 6 Mounting of Optional Accessories 20 SBT 2400 Installation Instructions M2041 5en BTG 2006 ...
Страница 58: ...5 4 Troubleshooting 52 SBT 2400 Service Instructions M2041 5en BTG 2006 ...