21 / 24
0006081484_201104
EN
GL
IS
H
PREPARATION FOR CONNECTION WITH
TRAIN TURNED UPWARDS
If you wish to turn the train entrance upwards, before applying the
burner to the boiler, follow the subsequent procedure.
1) Following the instructions detailed in the "Maintenance" para-
graph, extract the mixer assembly and remove the screw (1)
which connect the unit’s forward movement rod (2) to the gas
delivery pipe (3).
(3) Remove the screw (5) which connects the gas mixer (6) to the
pipe (figure 1).
2) Turn the bend coupling through 180° (4) and the mixer (6), in
such a way that the inlet gas is turned upwards (figure 1). Again
fix the mixer and the unit’s forward movement rod to the gas
delivery pipe.
3) Now remove the 4 nuts (7) in figure 2, disassemble the flame
pipe (8) from the relative stud bolts, reposition them with the
threaded connection for fixing the gas train upwards.
4) To complete the operation fix the flame pipe to the scroll burner
and finally reposition the mixing unit in the relative housing.
At this point it is possible to install the burner in the boiler with the
valve train as shown in configuration 9 illustrated in paragraph "Gas
train assembly".
fig. 1
fig-2
Содержание TBG 45 PN-V
Страница 2: ......
Страница 26: ...24 24 0006081484_201104 ENGLISH ...
Страница 50: ...24 26 0006081484_201104 ESPAÑOL ...
Страница 74: ...24 26 0006081484_201104 FRAÇAIS ...
Страница 98: ...24 24 0006081484_201104 TÜRKÇE ...
Страница 123: ...123 126 0006081484_201104 ...