COMMISSIONING
Before the H3000 Pilot can be used, it is necessary to carry out some
commissioning procedures. This encompasses the setting and calibration
of various parameters, installation and functional checks of the Pilot
equipment. These items are listed below.
The procedure for commissioning can be divided into two stages. The first
stage is carried out alongside at the dock and the second stage is
performed during the course of a sea trial. The order in which the
commissioning procedures are carried out is not the order in which they
appear in the menu.
This manual covers both the ACP 1 (25A) and ACP 2 (40A) Pilot
Systems.
Pilot Installation Check List
The checklist below should be used before the commissioning of
the Pilot to ensure that the entire system is functional before
applying power.
Drive Unit and Steering System
Drive unit securely fixed to a rigid part of the boat structure.
Correct gauge of power cable has been selected.
Hydraulic Rams
Mechanical end stops must limit the rudder movement, not the
stroke of the hydraulic ram.
Split pins and spacers that secure the ram to its mounting foot are
secure.
Absence of oil leaks.
Correct diameter bolt in universal ball joint, correct size hole in
tiller.
Ram free to move side to side and up and down throughout the
rudder travel.
Oil reservoir is at the highest point if external to the Ram.
Содержание H3000 Pilot
Страница 1: ...Pilot Handbook www bandg com ...
Страница 106: ......
Страница 115: ...___________________________________________________H3000 Pilot Handbook HB 3001 02 9 Type 1 and 2 Ram Drive Dimensions ...
Страница 117: ...___________________________________________________H3000 Pilot Handbook HB 3001 02 11 Type 3 Ram Drive Unit Dimensions ...
Страница 118: ...H3000 Pilot Handbook___________________________________________________ HB 3001 02 12 Type 3 Ram Bolt Detail ...