Manual, Control Module, PROFINET, DL10
Document #9620-20-C-DL10-04
Pinnacle Park • 1031 Goodworth Drive • Apex, NC 27539 • Tel: 919.772.0115 • Fax: 919.772.8259 •
C-24
Figure 3.1—Master Module Installation
Tool Changer
Valve Adapter (JT2-M Shown)
RTL, Lock,
and Unlock
Sensor Connectors
FE Ground Connection
with M8 set screw
(2) M6 Socket Head Cap Screw
L Connector
U Connector
R2 Connector
R1 Connector
Valve Signal
Pin Block
LEDs and
the Reset Switch
Use the Ledge Mounting Feature
to Properly Align the Module
Power
Connector
PROFINET
Connector
Master Module
3.2 Master Control/Signal Module Removal
Tools required: 5 mm Allen wrench (hex key)
1. Place the Tool in a secure location.
2. Uncouple the Master and Tool plates.
3. Turn off and de‑energize all energized circuits (e.g. electrical, air, water, etc.).
4. Disconnect the (L) Lock, (U) Unlock, and (R1 and R2) RTL sensor cable connectors from the Master
module.
5. Disconnect the power cable and PROFINET cable connectors from the Master module.
6. Disconnect the ground from the FE grounding terminal.
7. Support the control/signal module and remove the (2) M6 socket head cap screws and lower the module
until it clears the guide pin.
3.3 Tool Control/Signal Module Installation
Refer to
Tools required:
3 mm and 5 mm hex keys
Supplies required: Clean rag, Loctite 242, M5 fastener for grounding terminal
1. Place the Tool in a secure location.
2. Uncouple the Master and Tool plates.
3. Turn off and de‑energize all energized circuits (e.g. electrical, air, water, etc.).
4. Clean the mating surfaces.
5. Set the Tool‑ID. Refer to
Section 3.5—Setting the Tool‑ID.
6. Place the module into the appropriate location on the valve adapter spacer. Align the module with the
valve adapter spacer using the dowels in the bottom of the ledge feature. Refer to
.