Installation –
Preparing the installation site |
15
Preparing the installation site
As a matter of principle, the electrical supply cable in the domestic power distribution must be switched off for the
entire duration of mechanical and electrical installation. The connection to the power grid must only be made live for
the purpose of commissioning, after electrical installation is complete.
DANGER!
Dangerous electrical currents
Always observe the 5 safety rules:
1
Cut power source
2
Secure all cut-off devices
3
Verify absence of voltage
4
Ground and short-circuit
5
Cover or bar access to adjacent components under voltage
Proceed as follows:
1
Cut crosswise into the marks for the fixing points on
the drilling template using the utility knife.
2
Using the spirit level, align the drilling template level
and plumb on the mounting surface.
3
With the pencil, mark the fixing points in the mount-
ing position.
4
Pre-drill the marked fixing points with the electric
drill and drill bit (
∅
8 mm).
5
Drive the wall plugs into the fixing points with the
hammer.