If a test switch is not used, perform measurement according to the provided circuit diagrams.
Never disconnect the secondary connection of a current transformer circuit without
first short-circuiting the transformer's secondary winding. Operating a current
transformer with the secondary winding open will cause a massive potential build up
that may damage the transformer and cause personal injury.
9.4
Connecting the test equipment to the IED
M11744-2 v9
Connect the test equipment according to the IED specific connection diagram and the needed input
and output signals for the function under test. An example of a connection is shown in figure
.
Connect the current and voltage terminals. Pay attention to the current polarity. Make sure that the
connection of input and output current terminals and the connection of the residual current conductor
is correct. Check that the input and output logical signals in the logic diagram for the function under
test are connected to the corresponding binary inputs and outputs of the IED under test.
To ensure correct results, make sure that the IED as well as the test equipment are
properly earthed before testing.
IL1
IL2
IL3
IN
UL1
UL2
UL3
UN
IL1
IL2
IL3
UL1
IN (I4,I5)
TRIP L1
TRIP L2
TRIP L3
T
es
t e
qu
ip
m
en
t
IE
D
IEC09000652-1-en.vsd
UL2
UL3
UN
UN (U4,U5)
IEC 61850
IEC09000652 V1 EN-US
Figure 9:
Connection example of the test equipment to the IED when test equipment is
connected to the transformer input module
9.5
Releasing the function to be tested
M11413-2 v8
Release or unblock the function to be tested. This is done to ensure that only the function or the
chain of functions to be tested are in operation and that other functions are prevented from operating.
Release the tested function(s) by setting the corresponding
Blocked
parameter under Function test
modes to
No
in the local HMI .
When testing a function in this blocking feature, remember that not only the actual function must be
activated, but the whole sequence of interconnected functions (from measuring inputs to binary
output contacts), including logic must be activated. Before starting a new test mode session, scroll
Section 9
1MRK 506 377-UEN Rev. K
Testing IED operation
58
Railway application RER670
Commissioning manual
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Содержание Relion 670 series
Страница 1: ...Relion 670 SERIES Railway application RER670 Version 2 2 IEC Commissioning manual...
Страница 2: ......
Страница 22: ...16...
Страница 26: ...20...
Страница 38: ...32...
Страница 48: ...42...
Страница 54: ...48...
Страница 58: ...52...
Страница 72: ...66...
Страница 178: ...172...
Страница 186: ...180...
Страница 187: ...181...