2.2
Workflow
Start
ACT
SMT
PST
GDE
SMT
CMT
ACT
Export
SCD
IET600
Import
SCD
IED
WRITE
End
Project
IEC 61850
DNP3
IEC 60870-5-103
Make GOOSE connections
Export SCL files from
PCM600
Import SCL files to IET600
and do signal engineering.
Export updated SCL files
from IET600.
Import SCL files to PCM600
Configure IED functionality
Parametrization
Signal engineering
Create single line diagram
for local HMI
Save the work
between the
different steps
Create plant structure and
insert IED objects
Write configuration to IED
IEC09000623 V4 EN
Figure 4:
Protection relay engineering workflow
The described sequence is a proposal based on practical experience and dependencies
of the steps. It is possible to follow a different sequence based on the information
available at the time when the project is started. This means that several iterations may
be needed to complete the project.
Setting up a PCM600 project
•
The plant structure is built according to the substation structure.
1MRS756800 F
Section 2
Relay engineering process
630 series
17
Engineering Manual