![ABB HVC Скачать руководство пользователя страница 83](http://html.mh-extra.com/html/abb/hvc/hvc_installation-manual_1093083.webp)
HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2
COMPANY CONFIDENTIAL
Date released: 16-08-2018
Page
83
of
128
1. Check the delivery goods and boxes for damages.
2. Check that all cable connections on the pantograph and Wifi communication unit are tight.
WARNING
Make sure that the painted seal on the pantograph
electrical connectors are not damaged. Is this not the
case, contact ABB Delivery department (see
on Page 13 for contact details).
5.11.2.
Remove packaging
1. Remove the packing foil from the frames.
2. Open the front side of the wooden box with the plate work.
3. Keep the bag with bolts and nuts to assemble the pole in a safe place.
5.12.
Move the ABB pole to position
Preconditions:
The Charge control set are unloaded from the delivery truck.
The bolts of the foundation are free from dust. If necessary clean the bolts with a
vacuum cleaner or brush.
The work must be carried out by at least two persons.
DANGER
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system.
WARNING
Make sure that personnel cannot be crushed or get stuck while moving
the parts of the Charge control set.
WARNING
Make sure that personnel cannot be falling from the platform when
working at height.
CAUTION
Warranty
Damage due to moving the Charge control set to its position is not
covered by the warranty.
1. Lift the vertical frame by using two slings. The slings have to be attached to the top part
of the vertical frame as indicated below. Weight of the vertical frame is 1840.86 lb.