HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2
COMPANY CONFIDENTIAL
Date released: 16-08-2018
Page
109
of
128
6.
Commissioning
6.1. Commissioning preparation
Commissioning is the last phase necessary to get the HVC 450 kW E-Bus Charger into
operation.
The planning steps for the commissioning phase are shown in the figure below.
D
Commissioning
The commissioning of the HVC 450 kW E-Bus Charger need to be performed by a service
engineer from the ABB Delivery department and/or a certified local ABB service engineer.
Both will need the support from the local contractor.
Before the service engineer can start, the following conditions must be met:
All installation work is done.
Grid power is available.
A local technician is present for assistance and to switch the power on.
Boom lift available to check all the connections on the pantograph.
An electric or hybrid bus available to perform the functional tests.
CAUTION
Warranty
It is not permitted to move the whole or parts of the HVC 450 kW E-Bus
Charger after the commissioning. If the whole or parts of the HVC 450
kW E-Bus Charger is moved without contacting the ABB Service
department, the warranty will be considered void.