09 OPERATION
3BHS206977 E01 REV H
ACS1000I AIR-COOLED
USER MANUAL
119/174
9.6
Starting the drive
9.6.1
Checks before starting the drive
▲
DANGER
⚠
When the drive is put into service after it has been commissioned, or after it has been taken
out of service for a longer period, use the following checklist:
9.6.2
Starting the drive remotely
When the drive is operated from remote through a higher-level control system or an operator
control desk, follow the instructions in the appropriate manuals.
9.6.3
Starting the drive locally
1. Enable the local control mode of the drive.
2. Check that no alarm or fault messages are displayed on the CDP control panel.
- If a fault message is displayed on the CDP control panel, reset the fault.
It is recommended to have the following documents at hand when starting the
drive locally for the first time after commissioning:
- “Appendix D – Wiring diagrams” to identify the circuit breakers to be
switched on
- “10 CDP control panel” on page 125 for information on functions and features of
the CDP control panel
Hazardous voltages!
- All covers must be screwed in place to prevent unintentional contact with
energized components.
1.
Tools and foreign objects are inside the cabinet.
□
2.
All auxiliary power supplies from external sources are switched on.
□
3.
All internal circuit breakers of the drive are closed.
□
4.
All covers are mounted and the doors are closed, locked or bolted.
□
5.
Grounding switch is in the ungrounded position.
□
6.
MCB is in operating position.
□
7.
No run interlocks are active.
□
LOC
RESET
REF
REM
Содержание ACS1000i air-cooled
Страница 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000i air cooled User manual ...
Страница 3: ...Contents ACS1000i air cooled User manual ...
Страница 5: ... 01 About this manual 01 5 16 ...
Страница 16: ......
Страница 17: ... 02 Important safety information 02 17 28 ...
Страница 28: ......
Страница 29: ... 03 Power electronics and cabinet features03 29 56 ...
Страница 57: ... 04 Control system 04 57 70 ...
Страница 71: ... 05 Transportation storage and disposal05 71 78 ...
Страница 78: ......
Страница 79: ... 06 Mechanical installation 06 79 88 ...
Страница 88: ......
Страница 89: ... 07 Electrical installation07 89 104 ...
Страница 105: ... 08 Commissioning 08 105 110 ...
Страница 110: ......
Страница 111: ... 09 Operation 09 111 124 ...
Страница 125: ... 10 CDP control panel 10 125 148 ...
Страница 149: ... 11 Preventive and corrective maintenance 11 149 172 ...
Страница 173: ......