Getting Started | 17
Aprisa SRi User Manual 1.1.0
1.
Getting Started
This section is an overview of the steps required to commission an Aprisa SRi radio network in the field:
Phase 1: Pre-installation
1.
Confirm path planning.
Page 66
2.
Ensure that the site preparation is complete:
•
Power requirements
•
Tower requirements
•
Environmental considerations, for example, temperature control
•
Mounting space
Page 69
Phase 2: Installing the radios
1.
Mount the radio.
Page 72
2.
Connect earthing to the radio.
Page 71
3.
Confirm that the:
•
Antenna is mounted and visually aligned
•
Feeder cable is connected to the antenna
•
Feeder connections are tightened to recommended level
•
Tower earthing is complete
4.
Install lightning protection.
Page 71
5.
Connect the coaxial jumper cable between the lightning protection and the radio
antenna port.
Page 76
6.
Connect the power to the radio.
Page 77