![3Ware 720-0186-00 Скачать руководство пользователя страница 91](http://html1.mh-extra.com/html/3ware/720-0186-00/720-0186-00_manual_3239008091.webp)
Unit Object Commands
www.3ware.com
84
For 9550SX and earlier controllers and for 9650SE and 9690SA running
pre-9.5.1, when you issue this command the specified verify will begin if the
verify schedule is disabled; otherwise it will pause until the next scheduled
verify. If after starting a verify, you enable the Verify Task Schedule, this on-
demand task will be paused until the next scheduled timeslot.
For 9650SE and 9690SA controllers running firmware 9.5.1 or later, if
verify=basic, the verify will begin immediately. If verify=advanced, the verify
will pause until the next scheduled verify. For more information, see “/cx set
verify=advanced|basic|1..5” on page 68.
Verify will pause if a rebuild, migration, or initialization is currently in
progress.
/c
x
/u
x
pause rebuild
This command allows you to pause the rebuild operation on the specified unit
/c
x
/u
x
.
This feature is only supported on the 7000/8000 series controllers. 9000 series
controllers have an on-board scheduler where rebuild operations can be
scheduled to take place at specified start and stop times. The
/c
x
/u
x
pause
rebuild
command is provided to enable 7000/8000 users to achieve similar
functionality with use of Linux-provided schedulers such as cron(8) or at(1),
or user-supplied programs.
Table 10: Manual Verify Behavior (/cx/ux start verify)
9650SE and
9690SA with
9.5.1 or later
9650SE and
9690SA with
firmware 9.5 or
9.5.0.1
9550SX and
earlier
Basic Verify Schedule
(verify=basic)
Runs
immediately
N/A
N/A
Advanced Verify
Schedule
(verify=advanced)
Follows
Advanced Verify
Schedule
N/A
N/A
Verify Schedule is
Disabled
(verify=disable)
Runs
immediately
(Same as Basic)
Runs
immediately
Runs
immediately
Verify Schedule is
Enabled
(verify=enable)
Follows
Advanced Verify
Schedule
Follows Verify
Schedule
Follows Verify
Schedule