4.
The cabinets must be provided with anti-shock reinforcement, and secured to the
ground with anchor bolts when necessary.
5.
Board connectors should be in good contact, easy to plug in or out, and the surfaces
are flat after the boards are plugged in the slots.
10.2 Checking Cables
The contents to check cables are explained as follows.
l
Checking power cable cabling;
l
Checking intra-cabinet cabling;
l
Checking inter-cabinet cabling;
l
Checking optical fibers;
l
Checking outdoor cabling.
10.2.1 Checking the Connections
Connection inspection contains:
l
Checking the connection relations;
l
Checking the connection points.
10.2.1.1 Checking the Connection Relations
Referring to the table of cable connection relations, check whether both ends of the various
cables have been connected to the proper positions.
10.2.1.2 Checking Connection Points
Verify that the various connection points are firmly connection and in good contact
according to the following requirements.
1.
When fixing the cable lug, remember to add the plain washer and the spring washer
to secure it and ensure good contact between the cable and the busbar, and minimize
the contact resistance.
shows specific wiring method.
10-2
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential
Summary of Contents for ZXG10 iBSC
Page 8: ...II ...
Page 167: ...Figures Figure 11 7 Step 3 of Board Unplugging 11 5 V ...