ACCURA Installation site requirements
17
Wiring diagram for MCC 800 controller cabinet
We recommend installing the connection in accordance with the following diagram.
Note:
Comply with applicable national regulations.
C 16 A / 15 A
PE
L
N
PE
L
N
PE
N
L
X4100
C 16 A / 25 A
A
MCC 800
A
Customer installation of local voltage (suggested)
1
Circuit breaker [C 16 A/ 25 A]
2
Circuit breaker [C 16 A/ 15 A]
3
Recommended: residual current circuit breaker
4
Cable (included with delivery)
5
Main switch
6
Shock-proof outlet
Note:
For maintenance work on the CMM
Network connection
A network connection is required for:
–
Data backup
–
Teleservice (this is a ZEISS-recommended service and requires an Internet connection).
An Internet connection is not required for the installation of the CMM.
Network topology
System components are networked during start-up by a ZEISS service engineer (or a specialist authorized by ZEISS) in
accordance with the applicable specifications and must not be modified by the customer. Any change may lead to
connection problems.