Example:

An 80,000 BTUH furnace requires 32 feet of pipe and four 90º elbows.
Using 2" pipe and standard elbows, the total equivalent length will be:

This exceeds the 65 foot maximum equivalent length of 2" pipe allowed
for that model and is thus not acceptable.

By using sweep elbows, the total equivalent length will be:

This is less than the 65 foot maximum equivalent length of 2" pipe
allowed for that model and is thus acceptable. 

Alternatively, using 3" pipe and standard elbows, the total equivalent
length will be:

This is less than the 90 foot maximum equivalent length of 3" pipe
allowed for that model and is thus acceptable.

Dimensions are those required in Standard ASTM D-3311.

NOTE: 

Sidewall vent terminal may be used for sidewall vent termina-

tions. Refer to part list in the back of the USERS INFORMATION AND
SERVICE AND MAINTENANCE MANUAL for the terminal part number.

*. Vent pipe size must be increased to 3” diameter after connection to furnace 

on this model.

IMPORTANT: 

Accessory concentric vent / intake termination kits

1CT0302 and 1CT0303 are available and approved for use with these
furnaces. Horizontal sidewall vent terminations kits 1HT0901 &
1HT0902 are also approved for use with these furnaces.

IMPORTANT: 

Furnace vent pipe connections are sized for 2” (5.1 cm).

pipe. Any pipe size change must be made outside the furnace casing in
a vertical pipe section to allow proper drainage of condensate. An offset
using two 45º (degree) elbows will be required for plenum clearance
when the vent is increased to 3” (7.6 cm).

COMBUSTION AIR AND VENT PIPING ASSEMBLY

The final assembly procedure for the combustion air and vent piping is
as follows:

1.

Cut piping to the proper length beginning at the furnace.

2.

Deburr the piping inside and outside.

3.

Chamfer (bevel) the outer edges of the piping.

4.

Dry-fit the vent piping assembly from the furnace to the outside ter-
mination checking for proper fit support and slope.

5.

Dry-fit the combustion air piping assembly checking for proper fit,
support and slope on the following systems:

A.

Sealed combustion air systems from the furnace to the out-
side termination.

B.

Ventilated combustion air systems from the furnace to the
attic or crawl space termination.

6.

Disassemble the combustion air and vent piping, apply cement
primer and the cement per the manufactures instructions. Primer
and cement must conform to ASTM D2564 for PVC, or ASTM
D2235 for ABS piping.

7.

All joints must provide a permanent airtight and watertight seal.

8.

Support the combustion air and vent piping such that it is angled a
minimum of 1/4” per foot (0.635 cm/m) so that condensate will flow
back towards the furnace. Piping should be supported with pipe
hangers to prevent sagging.

9.

Seal around the openings where the combustion air and / or vent
piping pass through the roof or sidewalls.

COMBUSTION AIR / VENT CLEARANCES

IMPORTANT: 

The vent must be installed with the following minimum

clearances, and must comply with local codes and requirements.

TABLE 7: 

Equivalent Length of Fittings

Fitting

Equivalent Length

2" 90º sweep elbow

5 feet of 2" pipe

2" 45º sweep elbow

2-1/2 feet of 2" pipe

2" 90º standard elbow

10 feet of 2" pipe

2" 45º standard elbow

5 feet of 2" pipe

3" 90º sweep elbow

5 feet of 3" pipe

3" 45º sweep elbow

2-1/2 feet of 3" pipe

3" 90º standard elbow

10 feet of 3" pipe

3" 45º standard elbow

5 feet of 3" pipe

2" corrugated connector

10 feet of 2" pipe

3" corrugated connector

10 feet of 3" pipe

32 feet of 2" pipe =

32 equivalent feet

4 - 90º standard 2" elbows = (4x10) =

 40 equivalent feet

Total = 

72 equivalent feet of 2" pipe

32 feet of 2" pipe =

32 equivalent feet

4 - 90º standard 2" elbows = (4x5) =

 20 equivalent feet

Total = 

52 equivalent feet of 2" pipe

32 feet of 3" pipe =

32 equivalent feet

4 - 90º standard 2" elbows = (4x5) =

 40 equivalent feet

Total = 

72 equivalent feet of 3" pipe

 FIGURE 11:  

Dimensions

TABLE 8: 

Elbow Dimensions

Elbow

"A" Dimension

2" Standard

2-5/16"

3" Standard

3-1/16"

2" Sweep

3-1/4"

3" Sweep

4-1/16"

A

A

A

A

STANDARD ELBOW

LONG (SWEEP) ELBOW

TABLE 9: 

Combustion Air Intake and Vent Connection Size at Furnace 

(All Models)

FURNACE VENT CONNECTION SIZES

Furnace Input

60 - 100 MBH 

(17.5 - 29.3 kW)

120 MBH 

(35.2 kW)

Intake Pipe Size

2” (5.1 cm)

3” (7.6 cm)

Vent Pipe Size

2” (5.1 cm)

3” (7.6 cm)*

Solvent cements are flammable and must be used in well-ventilated
areas only. Keep them away from heat, sparks and open flames.
Do not breathe vapors and avoid contact with skin and eyes.

Summary of Contents for FC9C UP Series

Page 1: ...l codes LIST OF SECTIONS FURNACE DESCRIPTION 1 SAFETY 1 DUCTWORK 4 FILTERS 6 GAS PIPING 7 ELECTRICAL POWER 8 COMBUSTION AIR AND VENT SYSTEM 14 CONDENSATE PIPING 20 SAFETY CONTROLS 21 START UP AND ADJU...

Page 2: ...as listed under Clearances to Combustibles in Table 1 Provide clearances for servicing ensuring that service access is allowed for both the burners and blower These models ARE NOT CSA listed or appro...

Page 3: ...e floor and the furnace must be located or protected to avoid physical damage by vehicles The furnace area must not be used as a broom closet or for any other storage purposes as a fire hazard may be...

Page 4: ...OTE When attaching duct flange do not shoot the screw down into the casing Use the formed flange intended for duct flange attachment The duct system is a very important part of the installation If the...

Page 5: ...ndi cate the presence of leaks in the heat exchanger This access cover shall be attached in such a manner as to prevent leaks TABLE 2 Minimum Duct Sizing For Proper Airflow Input Airflow Return1 Recta...

Page 6: ...r this require the use of high velocity fil ters 2 Air flows above 1800 CFM require either return from two sides or one side plus bottom SIDE RETURN FILTER INSTALLATION Locate and mark the side return...

Page 7: ...l At elevations above 4 000 feet the furnace will automatically reduce it s input rate if necessary to maintain good combustion If the natural gas being supplied has also been derated by the gas suppl...

Page 8: ...o Furnace Diag nostics section of the User s Information Maintenance Ser vice Manual provided with this furnace LOW VOLTAGE CONTROL WIRING CONNECTIONS Install the field supplied thermostat by followin...

Page 9: ...age Compressor Y2 Second Stage Compressor C 24 Volt Common R 24 Volt Hot Y1 Single Stage Compressor VARIABLE SPEED MODULATING FURNACE CONTROL G Fan VARIABLE SPEED MODULATING FURNACE Y Y2 Second or Ful...

Page 10: ...Move HUMIDISTAT jumper to YES if humidistat is to be used FL9C FC9C PC9 ID MODELS External Humidistat Optional Open on Humidity Rise 24VAC Humidifier Optional External Humidistat Optional Open on Hum...

Page 11: ...n HM Humidistat Step 1 of Thermostat User Configuration Menu must be set to MLTISTG E W1 First Stage Heat 24VAC Humidifer Optional C 24 Volt Common R 24 Volt Hot Y1 Single Stage Compressor VARIABLE SP...

Page 12: ...l C 24 Volt Common R 24 Volt Hot Y1 Single Stage Compressor VARIABLE SPEED MODULATING FURNACE CONTROL G Fan VARIABLE SPEED MODULATING FURNACE Y Y2 Second or Full Stage Compressor HUM Dehumidification...

Page 13: ...09137 18395 031 01996 340512 031 09178 1 FL9C FC9C PC9 ID MODELS YZE OD MODELS YZH H 5 H 8 C 24 Volt Common R 24 Volt Hot Y1 First Stage Compressor O Reversing Valve Energized in Cool L Malfunction L...

Page 14: ...for a particular model then the vent can have 65 equivalent feet of pipe AND the combustion air intake can have another 65 equivalent feet of pipe 3 Three vent terminal elbows two for the vent and on...

Page 15: ...ystems from the furnace to the out side termination B Ventilated combustion air systems from the furnace to the attic or crawl space termination 6 Disassemble the combustion air and vent piping apply...

Page 16: ...ns 9 inches 23 cm for models 50 000 BTUH 15 kW 12 inches 30 cm for models 50 000 BTUH 15 kW C Clearance to permanently closed window 12 inches 30 cm 12 inches 30 cm D Vertical clearance to ventilated...

Page 17: ...ombustion air systems must be installed so the vent and the combustion air pipes terminate in the same atmospheric zone Refer to Figures 14 or 15 VENTING MULTIPLE UNITS Multiple units can be installed...

Page 18: ...ical vent Care should be taken to locate side vented systems where trees or shrubs will not block or restrict supply air from entering the terminal Also the terminal assembly should be located as far...

Page 19: ...ENTILATED ATTIC TOP ABOVE INSULATION OPTIONAL INLET a OUTLET AIR a VENTILATED CRAWL SPACE GAS WATER HEATER VENTILATED ATTIC TOP ABOVE INSULATION GAS VENT GABLE VENT SOFFIT VENT GAS WATER HEATER INLET...

Page 20: ...bustion Air The ventilated attic space or a crawl space from which the combustion air is taken must comply with the requirements specified in AIR SOURCE FROM OUTDOORS in this instruction or in Section...

Page 21: ...s sensor monitors combus tion airflow through furnace and piping systems If any of the conditions listed above are detected by the pressure sensor the control board will prevent a hazardous condition...

Page 22: ...ing any pressure testing of that system at test pres sures in excess of 1 2 PSI 3 45 kPa The furnace must be isolated from the gas supply piping system by closing the equipment shutoff valve during an...

Page 23: ...3600 then divided by the time it took to measure 0 10 m3 of gas from the gas meter For Propane LP Gas multiply the Heat content of the gas MJ m3 or Default 93 15 times 0 10 m3 of gas measured at the...

Page 24: ...nt screws on main gas valve 2 Turn gas and electrical supplies on and follow the operating instructions to place the unit back in operation 3 Adjust manifold pressure by adjusting gas valve regulator...

Page 25: ...s fan operation can be adjusted as desired This is done my moving the RECIRC jumper on the control board to give the desired airflow The jumper has three positions The A position delivers maximum air...

Page 26: ...rate 6 The firing rate is automatically adjusted to meet demand increas ing gradually to maximum 100 firing rate if the thermostat is not satisfied within a defined time 7 When the thermostat R and W...

Page 27: ...five minutes indi cating that the blower motor or blower wheel has failed Twelve Red Flashes ID plug is not present or not connected properly check for loose plug or loose wires in plug Steady On Red...

Page 28: ...730 530 22 4 16 1 20 7 15 0 C C 630 530 590 500 17 8 15 0 16 7 14 2 D C 80 000 100 000 INPUT 4 Ton 100 000 INPUT 5 Ton 80 000 100 000 INPUT 4 Ton 100 000 INPUT 5 Ton JUMPER SETTINGS CFM CFM m min m mi...

Page 29: ...50 w c 125 Pa to obtain a percentage 0 58 0 50 0 60 0 50 0 8 Multiply percentage by airflow difference to obtain airflow reduction 0 8 X 110 88 Subtract airflow reduction value to airflow 0 50 w c 125...

Page 30: ...A 292278 UIM A 0108 Copyright by Unitary Products Group 2008 All rights reserved Supersedes 172078 YIM C 0606 Unitary 5005 Norman Product York OK Group Drive 73069 SECTION XII WIRING DIAGRAM FIGURE 26...

Reviews: