2. Transportation, Storage and Installation
2-11
TI 33Q01J10-01E
2.5.1
Installation on Floor
The installation method varies with the type of the floor and building.
• After unpacked, be careful not to put any impact until it is fixed to the floor to prevent from
tip-over.
• Install devices as specified in the plans.
Check the position of front and back panels of the cabinet.
Avoid physical shock. Never use hammers.
• The open display style console assembly YPCKIT (excluding option code FT) is provided
with simple legs. When the YPCKIT is secured to the floor, remove and store the simple
legs. Use them at the time of movement in the future.
• Fix each equipment to the floor. The explanation below shows how to fix devices on different
types of floors.
Concrete Floor
Clamp the equipment to the floor using anchor bolts. It is recommended to use M12 bolts and
3200 N•cm tightening torque.
Equipment
Anchor bolts
F020401.ai
Figure Using Anchor Bolts
Steel Floor
Clamp the equipment to the floor using clamp bolts.
After cabling through the riser duct, fill the duct with rubber sponges and seal the top with putty.
Equipment
Steel floor
Clamp bolt
F020402.ai
Duct
Riser
Figure Using Clamp Bolts
Sep. 30, 2008-00