5 - 70
ENG
CONNECTING RODS AND PISTONS
▼▼▼
▼
▼ ▼▼▼
▼
▼ ▼▼▼
▼
▼ ▼▼▼
▼
▼ ▼▼▼
▼
▼ ▼▼▼
▼
▼▼▼
The following procedure applies to all of the
connecting rods.
CAUTION:
@
Do not interchange the big end bearings
and connecting rods. To obtain the correct
crankshaft-pin-to-big-end-bearing clear-
ance and prevent engine damage, the big
end bearings must be installed in their orig-
inal positions.
a. Clean the big end bearings, crankshaft pins,
and the inside of the connecting rod halves.
b. Install the big end upper bearing into the
connecting rod and the big end lower bear-
ing into the connecting rod cap.
NOTE:
@
Align the projections
a
on the big end bear-
ings with the notches
b
in the connecting rod
and connecting rod cap.
c. Put a piece of Plastigauge
®
1
on the crank-
shaft pin.
d. Assemble the connecting rod halves.
NOTE:
@
• Do not move the connecting rod or crank-
shaft until the clearance measurement has
been completed.
• Lubricate the bolts threads and nut seats
with molybdenum disulfide grease.
• Make sure that the “Y” mark
c
on the con-
necting rod faces towards the left side of the
crankshaft.
• Make sure that the characters
d
on both the
connecting rod and connecting rod cap are
aligned.
Summary of Contents for YZF-R1P 2001-2003
Page 1: ......
Page 2: ......
Page 3: ...YZF R1P YZF R1PC SERVICEMANUAL LIT 11616 15 47 5PW 28197 10...
Page 4: ......
Page 9: ......
Page 78: ...2 28 SPEC COOLING SYSTEM DIAGRAMS 1 Radiator...
Page 83: ...2 33 SPEC LUBRICATION DIAGRAMS 1 Main axle 2 Oil delivery pipe 3 Drive axle...
Page 84: ...2 34 SPEC LUBRICATION DIAGRAMS 1 Cylinder head 2 Crankshaft...
Page 439: ...YAMAHA MOTOR CO LTD 2500 SHINGAI IWATA SHIZUOKA JAPAN PRINTED IN U S A...