WARNING: FIRE HAZARD

All fuel runs should be installed by a licensed fuel supplier.

To connect the fuel line to the generator set you will 

connect your incoming fuel line to the 3/4 inch NPT fitting 

located on the left side of the engine-generator set. This 

fitting is shipped with a plastic plug installed to insure 

the fuel system stays clean. For all vapor fuel systems the 

delivery pressure of the fuel to the fuel solenoid on the unit 

must be four to six ounces psi (per square inch) or 7 to 11 

inches W.C. (water column). These fuel pressures are critical; 

failure to provide the proper pressure can cause many 

problems ranging from a unit that will not start to causing 

damage to the fuel system.

These units are normally tested on Natural Gas and will 

have a tag hanging on the fuel hose indicating on what 

fuel your unit was factory tested. If you are running on LP or 

have to change fuel types at any time, see information on 

page 7 on NG/LP CONVERSION. 

NOTICE

The engine generator sets are properly adjusted before they 

leave the factory. A tag is attached to the unit that specifies 

the fuel, natural gas (NG) or propane vapor (LP) that the 

unit was set up and tested on.

NATURAL GAS or LP VAPOR PIPE SIZE

Size of pipe normally required for generators operating on 

natural gas or LP vapor. Unit location will determine the 

size of fuel line that is required to supply the engine with a 

constant fuel pressure and volume.

LIQUID PROPANE VAPOR (LP)

Refer to the tables on the following pages for fuel line size 

and recommended tank size. For distances of 50 feet or 

over, a two regulator fuel system is recommended. This is 

accomplished by installing a primary regulator at the tank 

which will reduce the tank pressure down to 10 to 15 

lbs. A low pressure regulator is installed to further reduce 

the fuel pressure to the required four (4) to six (6) oz. 

operating pressure. This low pressure regulator must be 

at least 10 feet from the engine generator set; any closer 

installation will require a larger line be installed to provide 

a fuel reservoir. This is also true for the single low pressure 

regulator, it should also be a minimum of 10 feet from the 

unit. If this is not done, the demand regulator on the unit 

and the pressure regulator in the fuel line will interfere 

with each other. When the two (2) regulator system is 

used on LP, a fuel line size of 1/2 to 5/8 inch is generally 

adequate for distances up to 300 feet from the primary to 

the low pressure regulator. Consult your local fuel supplier 

for your exact requirements . The appropriate line size from 

the following table is then installed from the low pressure 

regulator to the generator set.

Feet*

Size of pipe

Up to 25 ft

¾” pipe

25 - 100 ft

1” pipe

Over 100 ft

Use a two regulator system

*Allow an additional 3 feet for each standard elbow. DO 

NOT use ‘street ells’ (restrictive).

 LP TANK SIZING

Tank Temperature

Tank Size

60° F (16° C)

150 Gallons

32° F (0° C)

250 Gallons

0° F (18° C)

500 Gallons

-20° F (-29° C)

1000 Gallons

NATURAL GAS (NG)

The primary regulator (fuel meter) on the building should 

deliver the correct volume and pressure to the generator 

set. This regulator must be sized to deliver the required 

BTU’s to the generator set and all other appliances in the 

building. If the primary regulator (fuel meter) is a high 

pressure regulator, then a low pressure regulator must be 

installed to bring the pressure down to 4-6 oz. (7-11 inches 

water column) of pressure. This low pressure regulator must 

be at least 10 feet from the engine generator set; any closer 

installation will require a larger line be installed to provide 

a fuel reservoir. If this is not done, the demand regulator 

on the unit and the pressure regulator in the fuel line will 

interfere with each other. This regulator must be sized to 

accommodate the demand of the generator set and any 

other appliance connected to it. See the following table for 

the correct size of pipe to be installed.

Feet*

Size of pipe

Up to 25 ft

¾” pipe

25 - 100 ft

1” pipe

Over 100 ft

Use a two regulator system

*Allow an additional 3 feet for each standard elbow. DO 

NOT use ‘street ells’ (restrictive).

WARNING: PERSONAL DANGER

Do not use galvanized pipe in fuel line runs. The galvanized 

coating can become eroded and flake off, causing possible 

obstructions in the regulator or fuel valve. The results could 

range from inoperative engine to hazardous fuel leaks.

CAUTION

Be careful when sealing gas joints. Excessive sealing 

compound can be drawn into the solenoid, regulator or 

carburetor causing an engine malfunction.

FUEL PRESSURE

Correct fuel pressure cannot be stressed enough. The most 

common cause for inoperative systems is an inadequate 

or incorrect fuel pressure. Performance of the engine is in 

direct relation to the correctness of the fuel system. Shown 

below is a diagram of a typical LP vapor fuel installation. 

Notice the following tables give two different units of 

measuring fuel pressure. The first and most accurate is 

the use of a simple water manometer. A manometer is 

calibrated in inches of water column . The second is with a 

pressure gauge calibrated in ounces per square inch. 

Summary of Contents for PSS8B2F

Page 1: ...o contact us concerning this unit it will help us to respond to your needs faster MODEL _________________________________________________ SERIAL NUMBER _________________________________________ PURCHA...

Page 2: ...WITCH ENGINE GENERATOR SET ENGINE MAINTENANCE MAINTENANCE SCHEDULE TROUBLESHOOTING 22 OUTLINE DRAWING 23 PAD LAYOUT DRAWING 24 AC WIRING SCHEMATIC 24 AC AND DC GENERATOR SCHEMATIC 25 SOLAR CONTROL PAN...

Page 3: ...t must be mixed with fresh air A Operate only in well ventilated areas B Never operate indoors including attached garages C Never operate the unit in such a way as to allow exhaust gases to seep back...

Page 4: ...er option derate 30 and note the circuit breaker derates to 25 Amp FUEL CONSUMPTION Natural Gas 1000 BTU FT LP Vapor 2520 BTU FT CF HR 132 63 BTU HR 132 000 158 760 GAL HR N A 1 6 Based on full load o...

Page 5: ...ment The ATS also contains the power failure sensing circuitry necessary to start and stop the engine generator set The transfer switch is also equipped standard with a 3 second start delay and a 15 s...

Page 6: ...crankcase the first time use the dipstick A in following image to ensure that you do not over fill the crankcase The full oil level mark on the dipstick is depicted in the following image as B Oil is...

Page 7: ...satisfactory system installation The information in this manual is offered only as a guide to finalizing your installation plans WARNING PERSONAL INJURY The enclosures on these units can become very...

Page 8: ...rimary to the low pressure regulator Consult your local fuel supplier for your exact requirements The appropriate line size from the following table is then installed from the low pressure regulator t...

Page 9: ...Natural gas Ref 2 3 4 Unit off Line PSI 7 11 in 4 6 oz 7 11 in 4 6 oz Starting Line PSI 7 11 in 4 6 oz 7 11 in 4 6 oz No load Line PSI 7 11 in 4 6 oz 7 11 in 4 6 oz Full load Line PSI 7 11 in 4 6 oz...

Page 10: ...sh off immediately with water 3 If electrolyte contacts the eyes flush immediately and thoroughly with water Seek immediate medical attention 4 Spilled electrolyte is to be washed down with an acid ne...

Page 11: ...be fused for 15 Amps Terminal block connections have been provided in the customer connection area of the engine generator set See following diagram NOTICE The battery tender is not intended to recha...

Page 12: ...als L3 L7 The neutral leads from all three locations are connected to the isolated terminal lugs on the sidewall of the cabinet This terminal block is labeled NEUTRAL and the terminal lugs are mounted...

Page 13: ...through 9 These terminals will accept 22 14 AWG stranded wire It is recommended that you use 16 AWG for distances up to 200 feet You need to run two 2 wires from the engine generator set to the transf...

Page 14: ...y Deep Sea Electronics Model 3110 is used on this generator set See following picture and look for more information stated within this manual MANUAL OPERATION Press and release the red Stop Reset butt...

Page 15: ...hanging the exercise without a load will be discussed later Be sure that conditions are safe to do this operation BYPASS TIME DELAY Use this button to cancel the active time delay or exercise period s...

Page 16: ...art and run the exerciser must be reset after the power is restored The ASCO 185 has settings that can be changed for various applications The dipswitch options are explained in the ASCO 185 Operator...

Page 17: ...17 60706 211 J SEQUENCE OF OPERATION UTILITY FAILURE...

Page 18: ...Auxiliary inputs can be user configured and will display he message as written by the user Fail to Start The engine has not fired after the preset number of start attempts Fail to Stop The module has...

Page 19: ...The fault must be removed and the Stop Reset button pressed to reset the module The icon will appear flashing in the display MODULE DISPLAY TIMER ICON When the module is controlling the engine startin...

Page 20: ...il level must always be checked before the engine is started Refer to page 7 of this manual for instructions on checking the oil level Take care to remove any dirt or debris from around the oil plug b...

Page 21: ...ked up engine generator set 9 Defective starter fuel solenoid relays ENGINE CRANKS BUT WILL NOT START 1 Improper fuel pressure being delivered to unit 2 Fuel supply shut off 3 Fuel supply empty 4 Defe...

Page 22: ...22 60706 211 J 36 50 28 00 29 75 36 00 27 375 28 375 OUTLINE DRAWING...

Page 23: ...23 60706 211 J PAD LAYOUT DRAWING 11075 00 20 60706 211 ENGINE GENERATOR SET PAD LAYOUT...

Page 24: ...24 60706 211 J AC WIRING SCHEMATIC...

Page 25: ...25 60706 211 J 11075 00 22 60706 211 AC AND DC GENERATOR SCHEMATIC AC AND DC GENERATOR SCHEMATIC...

Page 26: ...26 60706 211 J EXTERNAL RECEPTACLE ASSEMBLY IF EQUIPPED SOLAR CONTROL PANEL IF EQUIPPED...

Page 27: ...27 60706 211 J SOLAR PANEL ASSEMBLY IF EQUIPPED...

Page 28: ...does not cover travel time mileage or labor for removal or re installation of WINCO product from its application Normal wear and tear Costs of rental equipment WINCO does not warrant engines Engines a...

Reviews: