64
Maintenance Schedule
Perform the following procedures at the recommended intervals.
Operation
Operation
Every 8
Every 8
Hours
Hours
Every 50
Every 50
Hours
Hours
Every 500
Every 500
Hours
Hours
Check the oil level
X
Inspect the hoses and fittings
X
Clean the wye fitting with strainer
X
Change the oil
After the first 50 hours,
then every 500 hours.
Inspect the mounting hardware
X
Servicing the Oil
Check the oil level after every 8 hours of use. Change the oil after the first 50
hours of use and then every 500 hours there after.
Checking the Oil Level
1. Locate the oil level window to determine the oil level
and
2. Ensure that the oil level is centered in the window.
3. Add oil if necessary. Refer to:
.
Changing the Oil
Change the oil after the first 50 hours of operation and then every 500
hours thereafter.
Draining the Oil
1. Trip the circuit breaker. Refer
to:
"Tripping and Resetting the Circuit Breaker" on page 60
.
2. Remove the hardware that secure the pump to the mounting bracket
and set them aside (
).
3. Place a container under the pump that is large enough to collect all
the oil that drains from the oil reserve.
4. Loosen and remove the drain plug on the bottom of the pump
).
Drain the lines before
servicing.
Liquid ejected at high
pressure can cause
serious injury.
High Pressure
•
•
1
1
1. Hardware
Figure 44