Phosphate Treatment
If Phosphate levels are higher than 1.0ppm, then;
Treat the high phosphate levels as an event, and complete a shock dose treatment using
Perox Perfect once the system has been commissioned.
There should be no need to treat phosphates regularly with any other chemicals other than
Perox Perfect, provided Perox pH control is used to control the pH.
Diatomaceous Earth filters are not recommended for use with Hydrogen Peroxide.
Copper ionisers can be used in conjunction with the Oxiswim system, but total copper levels
must not exceed 1ppm.
5.3
Planning
Before commencing the installation, take time to plan;
•
That the chemical drums will be at least 1.5m (5 ft.) apart.
•
Ensure the unit is protected from the weather and, when possible, not exposed to
elements.
Summary of Contents for OXISWIM
Page 1: ...D U A L S A N I T I S A T I O N Installation and Operation manual Version 1 1 3 December 2022 ...
Page 11: ...OXISWIM MANUAL P a g e 11 45 INSTALLATION AND COMMISSIONING ...
Page 15: ...OXISWIM MANUAL P a g e 15 45 Oxiswim Typical Installation Layout ...
Page 28: ...OXISWIM MANUAL P a g e 28 45 OPERATION AND MAINTENANCE ...