STEP 3 – Electrical Checks
Ensure the guidelines listed in Section 3 of this manual have been followed, paying particular
attention to the fuse rating, RCD and grounding requirements of the appliance.
Electrical cables including the cable for the user interface controller should be identified, routed
and secured in compliance with current codes of practice, keeping the AC cables and User
Interface Controller cable separate to avoid electrical interference.
Use of cable glands is recommended to ensure cable security and reduce the risk of cable
damage.
STEP 4 – Assignment of Required Parameters.
To ensure correct operation of the unit, several site-specific parameters must be assigned to the
appliance via the Engineer menu of the user interface controller before the unit is fired for the
first time. These parameters may be assigned by accessing the ‘1. Parameters’ utility within the
Engineer menu.
The Commissioning menu contains additional functions that should not be required
during normal machine installation checks – see WS18/WP18 technical manual for
further information.
•
From the home screen (Figure 64), press the
‘Program key’ to view the main menu.
•
Scroll to “5. Engineer” in the Main Menu using the ‘Down Arrow’ and confirm selection
using the ‘Enter key’. (Figure 65)