FF 424 FLANGE FACING SYSTEM
B. FLANGE FACER TO BEVELING
MACHINE CONVERSION PROCEDURE
1. Remove the flange facer mandrel from the
machine body. (Figure 1)
2. Remove the flange facer tool slide module,
by removing the four
3/8-16
x 1 -1/4” SHCS
using the provided hex key set. (Figure 2)
(Figure 1)
NOTE
:When reinstalling the trip ring assembly,
center cut out relief on trip ring over the air motor
housing for proper trip lever location. Be sure that
ring sits flush against housing all around.
3. Remove the trip collar assembly from
the flange facer machine housing by loosen-
ing the six locking socket set screws.
(Figure 3)
(Figure 2)
4. Mount rotating tool holder plate on machine
rotating
NOTE:
Be sure to install the felt washer.
Coat the washer with light oil. Place
into recessed hole in rear of tool holder
plate.
Align dowel pin holes in plate with the dowel
pins on the machine head and insert plate.
(Figure 3)
SECTION V
FF 424 SET UP AND OPERATING PROCEDURES
(Figure 4)
14.
34
Summary of Contents for FF 424
Page 2: ......
Page 6: ...SDB 412 and FF 424 4 Part No 66 MAN 01 Rev A E H Wachs...
Page 12: ...SDB 412 and FF 424 10 Part No 66 MAN 01 Rev A E H Wachs...
Page 24: ...22...
Page 40: ...SDB 412 and FF 424 38 Part No 66 MAN 01 Rev A E H Wachs SDB 412 Air Drive 66 000 01 NOTE...
Page 48: ...SDB 412 and FF 424 46 Part No 66 MAN 01 Rev A E H Wachs...
Page 66: ...SDB 412 and FF 424 66 Part No 66 MAN 01 Rev A E H Wachs...
Page 69: ......
Page 70: ...600 Knightsbridge Parkway Lincolnshire IL 60069 847 537 8800 www ehwachs com...