FF 424 FLANGE FACING SYSTEM
19. Using the infeed indice guage, rotate the
axial feed handles clockwise until the de-
sired depth of cut is attained. (Figure 17)
SECTION V
FF 424 SET UP AND OPERATING PROCEDURES
(Figure 17)
(Figure 18)
(Figure 19)
(Figure 20)
22. Now, time the starwheel. In order to prevent
damage to machine, the star wheel must be
timed prior to engaging any trips. (Figure 20)
20. Tighten the machine /mandrel locking set
screws with the provided hex key set.
(Figure 18)
IMPORTANT:
Tighten both locking set screws equally. Apply ten-
sion
in
order to pre-load machine to mast, allow
axial feed handles to rotate while also under ten-
sion
21. Engage the desired number of trips on the
trip collar. assembly to achieve the surface finish
required. (Figure 19) (Refer to flange surface trip
chart.)
NOTE:
A
general rule of thumb is to take light cuts
to clean up the flange face. To produce a 500
RMS or record groove finish, best results are
achieved with a finish cut depth of .007” to
.008”
23. The machine is now ready to cut. Press the
air motor lever to begin cutting.
13.
33
Summary of Contents for FF 424
Page 2: ......
Page 6: ...SDB 412 and FF 424 4 Part No 66 MAN 01 Rev A E H Wachs...
Page 12: ...SDB 412 and FF 424 10 Part No 66 MAN 01 Rev A E H Wachs...
Page 24: ...22...
Page 40: ...SDB 412 and FF 424 38 Part No 66 MAN 01 Rev A E H Wachs SDB 412 Air Drive 66 000 01 NOTE...
Page 48: ...SDB 412 and FF 424 46 Part No 66 MAN 01 Rev A E H Wachs...
Page 66: ...SDB 412 and FF 424 66 Part No 66 MAN 01 Rev A E H Wachs...
Page 69: ......
Page 70: ...600 Knightsbridge Parkway Lincolnshire IL 60069 847 537 8800 www ehwachs com...