Commissioning steps
Inspection steps
Maintenance steps
Page
•
1. Filling the heating system
................................................................................................. 26
•
•
•
2. Checking all connections on the heating water side for leaks
•
3. Switching on the power and starting the commissioning sequence
............................ 27
•
4. Selecting the language
...................................................................................................... 27
•
•
5. Setting the date
.................................................................................................................. 27
•
•
6. Setting the time
.................................................................................................................. 27
•
•
7. Selecting the number of buffer temperature sensors
..................................................... 27
•
•
8. Selecting the type of heating water buffer cylinder
........................................................ 27
•
•
9. Selecting an additional boiler
........................................................................................... 28
•
•
10. Selecting the connection for heating circuits 1 to 3
....................................................... 28
•
•
11. DHW connection
................................................................................................................. 28
•
•
12. Selecting DHW circulation (if heating circuit extension module installed)
.................. 28
•
•
13. Selecting the solar connection
......................................................................................... 28
•
•
14. Selecting the solar type
..................................................................................................... 29
•
•
15. Changing the heating circuit designations
...................................................................... 29
•
•
16. Diagnosis (if heating circuit extension module installed)
.............................................. 29
•
17. Checking the outputs and actuators
................................................................................ 29
•
•
18. Calibrating the O
2
probe
.................................................................................................... 30
•
•
19. Ending commissioning
...................................................................................................... 30
•
•
20. Displaying the menu structure
.......................................................................................... 31
•
21. Matching the control unit to the heating system
........................................................... 31
•
22. Adjusting the heating curves
............................................................................................ 31
•
23. Heat up
................................................................................................................................ 33
•
•
24. Shutting down the system
................................................................................................. 33
•
•
25. Hopper cleaning (if required)
............................................................................................ 35
•
26. Cleaning the secondary heating surfaces
....................................................................... 36
•
•
27. Cleaning the ash chamber and combustion chamber
.................................................... 37
•
•
28. Checking the packing cords
............................................................................................. 37
•
•
29. Checking the doors for tightness
..................................................................................... 38
•
30. Cleaning the flue gas fan
................................................................................................... 39
•
31. Cleaning the Lambda probe and air dampers
................................................................. 40
•
•
32. Cleaning the air box and secondary air supply
............................................................... 42
•
•
33. Cleaning the sensor well for flue gas temperature sensor
............................................ 43
•
•
34. Checking the expansion vessel and system pressure
................................................... 43
•
•
•
35. Checking the safety valve function
•
•
•
36. Checking the function of the thermally activated safety valve
...................................... 44
•
•
•
37. Checking the installation room ventilation air aperture
•
•
38. Test run
............................................................................................................................... 44
•
•
•
39. Emissions test
.................................................................................................................... 44
Commissioning, inspection, maintenance
Steps - commissioning, inspection and maintenance
5777 985 GB