8
E
Primary circuit flow (heat pump
brine inlet)
F
Secondary circuit flow (heating
water)
G
Secondary circuit return (heating
water)
H
Solar circuit flow
K
Solar circuit return
1.
Prepare the connections on the heat-
ing water and the DHW side.
Flush the heating system.
Connection of hydraulic pipes
D
to
G
:
■ On-site connection:
Use straight pieces of pipe (stand-
ard delivery).
■ With the connection set primary cir-
cuit/secondary circuit (accesso-
ries):
Use pipe bends from the connec-
tion set.
2.
Prepare the electrical connections.
Pipe lengths:
■ Required pipe length inside the appli-
ance plus wall clearance
2.25 m
■ Height, wall outlet:
2100 mm (see "Technical guides for
heat pumps")
Recommended power cables:
Type BWT/BWT-M
242.A06
242.A08
242.A10
Heat pump control unit
230 V~
Cable cross-section
■ Without power-OFF
3 x 1.5 mm
2
3 x 1.5 mm
2
3 x 1.5 mm
2
■ With power-OFF
5 x 1.5 mm
2
5 x 1.5 mm
2
5 x 1.5 mm
2
Compressor
Cable cross-section
■ 400 V~
5 x 2.5 mm
2
5 x 2.5 mm
2
5 x 2.5 mm
2
■ 230 V~
3 x 4 mm
2
3 x 4 mm
2
3 x 4 mm
2
Max. cable length
25 m
25 m
25 m
Instantaneous heating water
heater
8.8 kW
Cable cross-section
■ 400 V~
5 x 2.5 mm
2
5 x 2.5 mm
2
5 x 2.5 mm
2
■ 230 V~
7 x 2.5 mm
2
7 x 2.5 mm
2
7 x 2.5 mm
2
Max. cable length
25 m
25 m
25 m
Preparing for installation
Requirements concerning on-site connections
(cont.)
5601 598 GB
Summary of Contents for BWT 241.A Series
Page 20: ...20 aCH 11 10 193C SLP N 224 6 9 Installation sequence Siting the heat pump cont 5601 598 GB...
Page 22: ...22 4x 4x 6x 2x 22 19 21 20 Installation sequence Siting the heat pump cont 5601 598 GB...
Page 23: ...23 4x 23 2x 26 25 24 Installation sequence Siting the heat pump cont 5601 598 GB Installation...
Page 27: ...27 C D BB Installation sequence Siting the heat pump cont 5601 598 GB Installation...
Page 71: ...71 Opening programming unit 2 2x 1 3 Troubleshooting Repairs cont 5601 598 GB Service...
Page 123: ...123 5601 598 GB...