Chapter 2 - Installation
19. Align load frame, center pivot bearing, and pivot arm as shown in Figure
2-6.
20. Bolt pivot arm to load frame using 3/4-10 x 2 1/2-inch bolt, washer, and
nut in four places.
21. Install eccentric cam followers, 1-3/8 washers, 1-14 nuts, and grease
fittings in the four bottom holes of load frame.
Figure 2-6. AZ/EL Assembly, 4.5 Meter Motorized (Sheet 1 of 5), 482045B
42S199F
2-16