22
1.
Closing
2.
Axis of handle
3.
Handle
4.
Flexible circlip
5.
Securing nut
6.
Washer
7.
Setscrew
8.
Blind flange
9.
Locking screw of the handle
10. Locking screw of closing
11. Counterpart of closing
12. Sealing cord
13. Sealing surface of feed hopper
Fig.no. 12
Setting of the handle of ash pan door and stoking door
4.2
Putting the boiler into operation
1.
Make a fire in boiler
2.
Bring the boiler to the necessary operating temperature. The recommended temperature of the output
water is 80 °C.
3.
Switch on the exhaust ventilator
4.
Check the functionality of two way safety valve DBV 1 – 02
5.
Operate the boiler in operating state according to appropriate standards.
6.
Check again the boiler for leakage
7.
Make the user acquainted with operation and maintenance
8.
Make a record in the Guarantee certificate.
Summary of Contents for Hercules P 1
Page 1: ...Hercules U26 Návod k obsluze Hefaistos P 1 MANUAL FOR BOILER OPERATION AND INSTALLATION ...
Page 44: ...44 ...
Page 46: ...46 ...
Page 47: ...47 ...
Page 48: ...48 Update Date 42 2012 GB ...