35
Fold
fl
at
standoffs
Standoffs installed
Standoff
Only quali
fi
ed licensed or trained personnel
should install this appliance.
Installation
Unpack the Appliance
Beware of sharp edges! Wear gloves!
1. Remove the cardboard wrapping and the wood
pallet from the appliance and discard.
2. Unpack any loose items from around the appliance.
3. Verify that you have all the components
required for the installation,
including:
- approved non combustible cement board;
-
liners and fuel bed (in separate carton);
- trim kit with barrier screen;
- venting components and accessories;
-
optional LDK Duct Kit if used;
- electrical components if installing optional
decorative light wall switch or blower.
Install the Standoffs
The standoffs are supplied
fl
at on the
fi
rebox sides and
fi
xed at one end. Swivel up the
fl
at standoffs, bend
them as shown and
fi
x the loose end to the top of the
fi
rebox.
Installer—READ THIS FIRST
1. YOU NEED TO KNOW FROM THE
HOMEOWNER:
- Will the optional LDK Duct Kit be used;
- The height of the unit and hearth if used;
- The thickness and type of the wall
fi
nish
around the
fi
rebox opening;
- What accessories (trim, decorative lighting,
etc.) will be installed with this
fi
replace;
- The venting con
fi
guration.
2. Unpack the appliance, removing all items packed
inside and around the appliance.
3. Check that you have everything, using the Pack
Content sheet. Also, check that you have:
◊
a fuel bed (packed separately)
◊
a set of liners (packed separately)
4. Finish the framing.
5. Fit the appliance into framing.
6. Fix the appliance to the framing.
7. Install the optional LDK Duct Kit if used.
8. Remove the window of the appliance.
9. Install the venting system and tape vent pipe joints.
10. Position the restrictor.
11. Connect the electrical wiring for optional electric
accessories if used.
12. Install the optional electric accessories if used.
13. Connect and test the gas supply.
14. Install the liners.
15. Install the middle platform supports.
16. Install the fuel bed.
17. Re
fi
t the window and the hot glass safety plate
if removed.
18. Install the control wall switch kit.
19. Initialize the remote control system.
20. Verify the operation and adjust aeration settings.
21. Install the remote control handset wall holder.
22. Instruct the homeowner on the operation and
maintenance of the
fi
replace.
23. Finish the wall around the
fi
replace.
24. Install the surround trim
and barrier screen
.
Installation Planning
QUALIFIED
INSTALLER