4 Set-up
10
Installation
and
maintenance
instructions
ecoTEC
pro
0020244995_02
4.3
Transporting the product
4.3.1
General
▶
Hold the load as close as possible to your body. Do not
twist your body
–
instead, reposition your feet.
▶
If the unit is being lifted by two persons, ensure your
movements are coordinated during lifting.
▶
Avoid bending your upper body
–
do not lean forwards or
to the side.
▶
Wear appropriate cut-resistant and non-slip gloves to
protect yourself against sharp edges and maintain a safe
and secure grip.
▶
If required, get somebody to assist you in this.
4.3.2
Unloading the box from the delivery van
▶
It is recommended that two people lift the unit together.
▶
Lift the box using the straps provided.
▶
Use safe lifting techniques
–
keep your back straight and
bend your legs at the knee.
▶
Hold the load as close as possible to your body.
▶
If the unit is being lifted by two persons, ensure your
movements are coordinated during lifting.
▶
If required, get somebody to assist you in this.
4.3.3
Transporting the box from the delivery
point to the installation site
–
ground floor
▶
It is recommended that two people lift the unit together.
▶
Use safe lifting techniques
–
keep your back straight and
bend your legs at the knee.
4.4
Dimensions
720
20
624
160
125
188
100
100
35
35
440
A
338
180
125
2
1
3
5
7
9
8
4
6
6
4
7
11
10
3
5
12
1
Flue pipe wall duct
2
Product holder
3
Heating flow (22
×
1.5
diameter)
4
Hot water connection
(15
×
1.5 diameter)
5
Gas connection
(15
×
1.5 diameter)
6
Cold water connection
(15
×
1.5 diameter)
7
Heating return (22
×
1.5
diameter)
8
R1 tundish/condensate
trap connection
9
Flue pipe connection
10
Condensate discharge
connection, 19 mm
diameter
11
Condensate trap
12
Drain line/heating ex-
pansion relief valve
connection, 15 mm dia-
meter