Mounting and electrical installation
Set the F address at the module [
28].
Please assure the proper closing of the protective cover over the rotary coding switches
[
Mount the device according to the instructions [
16].
Connect Ethernet cables according to the instructions [
Connect the power supply according to the instructions [
20].
Wire the in- and outputs depending on their use [
Seal unused connectors with the respective protection caps [
19].
Connecting the supply voltage
Before the operating voltage is applied, assure that:
- no wiring or grounding errors exist
- a safe grounding of the device/of the application is guaranteed
Connect the supply voltage.
Check if all supply voltages as well as the output voltage are in the permitted range.
Check if the device works properly or if errors are displayed by controlling the diagnostics
an status displays.
7.1.2
Configuring in Turck Safety Configurator
Configure the device as described in chapter “Configuring the device” [
7.1.3
Commissioning the device at the PLC
Configure the device in the PLC.
Configure the device in the PLC configuration software [
58].
Load parameterization and configuration data via the PLC into the device.
Execute a functional test.
Check if the device works according to the configuration and if all safety functions react
as expected.