Site Preparation/Foundation
A
QuadGuard
®
M Wide,
for permanent applications, should be assembled on an existing or freshly
placed and cured concrete base (28 MPa [4000 psi] minimum). Location and orientation of the
concrete base and attenuator must comply with project plans or as otherwise determined by the
local highway authority.
Recommended dimension and reinforcement specifications for new concrete foundations are
provided in Trinity Highway concrete foundation drawings, supplied with the system. The system
may also be assembled on reinforced or non-reinforced concrete roadway (minimum 8” [200 mm]
thick). Deployment cross-slope shall not exceed 8% and should not twist more than 2% over the
length of the system; the foundation surface shall have a light broom finish.
Warning:
It is the responsibility of the installer to ensure proper site grading for
the QuadGuard
®
M Wide
placement as dictated by the state or specifying agency
pursuant to the AASHTO Roadside Design Guide.
Caution:
Accurate placement of all steel rebar is critical to avoid interference with
the concrete anchor bolts.
Warning:
Location of the Backup in relation to nearby objects will affect the
operation of the attenuator. Upon impact, the Fender Panels telescope rearward
and extend beyond the rigid Backup as much as 30” [762 mm]. Position the Backup
so that the rear ends of the last Fender Panels are a minimum of 30” [762 mm]
forward of objects that would otherwise interfere with movement of the rearmost
Fender Panels. Failure to comply with this requirement is likely to result in system
performance which has not been crash tested pursuant to MASH criteria and may
also cause component damage which will necessitate maintenance or
replacement of the system.
Important:
QuadGuard
®
M Wide
cannot be mounted on asphalt.
Figure 8
Cross-Slope
8% (5
○
) (12:1)
MAXIMUM
LEVELING PAD
(SHOWN EXAGGERATED
FOR CLARITY)
Summary of Contents for QuadGuard M Wide
Page 1: ......
Page 44: ...TrinityHighway com 43 Revision D March 2021 Concrete Pad 618686...
Page 45: ...TrinityHighway com 44 Revision D March 2021 TS Concrete Pad 8 w Rebar 618686...
Page 46: ...TrinityHighway com 45 Revision D March 2021 TS Concrete Pad 8 wo Rebar 618686...
Page 47: ...TrinityHighway com 46 Revision D March 2021 Tension Strut Backup 627528...
Page 48: ...TrinityHighway com 47 Revision D March 2021 Monorail Assembly 625637...
Page 49: ...TrinityHighway com 48 Revision D March 2021 Diaphragm Assembly 627534...
Page 50: ...TrinityHighway com 49 Revision D March 2021...
Page 51: ...TrinityHighway com 50 Revision D March 2021...
Page 52: ...TrinityHighway com 51 Revision D March 2021 Shim Kit 627518...
Page 53: ...TrinityHighway com 52 Revision D March 2021 Fender Panel Assembly 608241...
Page 54: ...TrinityHighway com 53 Revision D March 2021 Nose Assembly 627522...
Page 55: ...TrinityHighway com 54 Revision D March 2021 End Shoe Transition 627729...
Page 56: ...TrinityHighway com 55 Revision D March 2021 31 W Beam Guardrail Transition QFMTSCVR TWLR...
Page 57: ...TrinityHighway com 56 Revision D March 2021 Thrie Beam Transition QFMTSCVR TTLR...
Page 58: ...TrinityHighway com 57 Revision D March 2021 Safety Shape Barrier Transition QFMTSCVR T4LRF...
Page 59: ...TrinityHighway com 58 Revision D March 2021 Single Slope Transition QFMTSCVR T6LRF...
Page 60: ...TrinityHighway com 59 Revision D March 2021 QuadGuard M Wide TS w Block QFMTSCVR UVB...
Page 61: ...TrinityHighway com 60 Revision D March 2021 Vertical Barrier Transition QFMTSCVR ESLR...
Page 62: ...TrinityHighway com 61 Revision D March 2021 TS Concrete Pad w Block 627903...
Page 63: ...TrinityHighway com 62 Revision D March 2021...
Page 64: ......