18
14.03.2022
TNX65/42
General information
Power supply
The directives and regulations applicable in the country of use must
be followed.
The power supply cord to the machine should be as short as possible.
Use a sufficient wire size.
The power supply for the machine requires stable mains conditions; the max.
allowed operating voltage fluctuations are +10% or -10%.
The mains line must comply with the regulations of the local electricity supplier
and the VDE directives.
Main circuit breaker
Check that the building connection has sufficient capacity to cover
the additional load to be protected.
Discuss any unclear conditions with your local electricity supplier.
The main circuit breaker is not included in the delivery of the machine.
It must be installed outside the machine according to DIN EN 60204-1.
If a pre-transformer is required, the main circuit breaker must be installed after the
pre-transformer, i.e., on the secondary side. The fuse protection on the primary
side must be designed according to the connection data of the pre-transformer.
The loads to be protected depend on the existing operating voltage.
For the information on machine connection, operating voltage, main fuse, see
the electrical diagrams or Chapter
Electrical connection
.
External data transfer
Data cables must not be routed directly next to live cables.
For data transfer to/from external computers or servers/storage devices, suit-
able metal conduits must be installed for the data lines.
The connection to the internal network (DNC) requires an RJ45 network cable.
An additional connection to the external network (IoT) must be made with a
separate RJ45 network cable.
Summary of Contents for TNX65/42
Page 6: ...6 14 03 2022 TNX65 42 Table of Contents...
Page 10: ...10 14 03 2022 TNX65 42 Safety...
Page 20: ...20 14 03 2022 TNX65 42 General information...
Page 44: ...44 22 10 2021 TNX65 42 Installing the machine Transport retainer for workpiece handling...
Page 45: ...45 22 10 2021 TNX65 42 Installing the machine Transport retainer for tool changer if necessary...
Page 46: ...46 22 10 2021 TNX65 42 Installing the machine...
Page 54: ...54 10 2016 TNX65 42 Fuels...
Page 56: ...56 10 2016 TNX65 42 Pneumatic connection...