RTAF-ADF001A-EN
1
Sintesis™ RTAF
Installation Completion Check Sheet and Request for Trane Service
Important:
A copy of this completed form must be submitted to theTrane service agency that will be responsible for the start-
up of the chiller. Start-up will NOT proceed unless applicable items listed in this form have been satisfactorily
completed.
See unit IOM RTAF-SVX001*-EN for detailed installation instructions.
To:
Trane Service Office:
S.O. Number:
Serial Numbers:
Job/Project Name:
Address:
The following items are being installed and will be completed by:
Important:
Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up of Trane
®
products. Contractor shall provide Trane (or an agent of Trane specifically authorized to perform start-up) with
notice of the scheduled start-up at least two weeks prior to the scheduled start-up.
Check boxes if the task is complete or if the answer is “yes.”
1. Chiller
Installation meets foundation requirements.
In place and piped.
Isolation pads or elastomeric pads installed (optional).
2. Piping
Water piping flushed before making final connections to the system
Chilled water piping connected to:
Evaporator
Air handling units
Pumps
Flow switch or flow proving device installed
Strainer installed in entering evaporator water piping and cleaned
Water supply connected to filling system
Systems filled
Pumps run, air bled from system
Relief valve ventilation piping installed (if applicable)
Flow balancing valves installed in leaving chilled water
Gauges, thermometers and air vents installed on both sides of evaporator
3. Wiring
Wire size per submittal and NEC
Full power available, and within utilization range
External interlocks (flow switch, pumps auxiliary, etc.)
Chilled water pump (connected and tested)
115 Vac power available for service tools (recommended)
All controls installed and connected
4. Testing
Dry nitrogen available for pressure testing
Trace gas amounts of R-134a or R-513A available for leak testing (if required)
5.
Refrigerant on job site (if nitrogen charge option, model number digit 16 = 3 or 4, is chosen)
6.
Systems can be operated under load conditions
7.
Heaters
If unit was factory charged (model number digit 16 = 1 or 2),
energize heaters for 24 hours prior to start up
.
Important:
It is required that chiller heaters are energized for a minimum of 24 hours prior to start up.
Therefore, chiller should have power for this amount of time beforeTrane Service arrives to do start-up.
If unit has nitrogen charge (model number digit 16 = 3 or 4), contact Trane Service for unit charging prior to start-up.