Vertical Unit 

Before beginning: 

Be  sure  to  check  the  tightness  of  all  bolts, 

nuts and setscrews, which could have loosened 
during shipping. 

Rotate  blower  fan  shafts  by  hand  to  make 

certain  there  is  no  interference  or  rubbing 
between components. 

Verify  installation  surface  is  level  before 

proceeding with unit installation. 

Locate mounting hardware: 

Items  included:  Caulk,  Caulk  Tape, 

Fasteners 

Field  Supplied  Hardware:  Anchoring  studs 

along with nuts and washers 

Check all sections, of the unit, thoroughly for 

assembly  hardware.    The  assembly  hardware 
will  be  found  packaged  in  either  a  clear  plastic 
bag or corrugated box.  

 

NOTICE: There may be more than one 
package  of  assembly  materials 
provided. 

 

 

 

1. Anchor the stand on a level concrete pad 

using studs or by other means. Each stand foot 
pad needs to be secured. 

 

NOTICE:  For  indoor  equipment,  the 
stand  must  be  enclosed  (sometimes 
height  is  increased.)  A  transition  (by 
others)  must  be  made  from  enclosed 
stand  intake  opening  to  the  intake 
damper  or  louver  (a  size  variation  may 
exist.)  

 

Flat & Level 
Concrete Pad 

Set in Place Stud or 
Wedge Type Anchor 

Flat 
Washer 

Hex Nut 

Summary of Contents for TA-109

Page 1: ......

Page 2: ......

Page 3: ...void in event the product is improperly installed and or operated under conditions other than normal published ratings improperly maintained misused or not in compliance with applicable codes or not...

Page 4: ...rvation and are not intended to supplant requirements of federal state or local codes having jurisdiction These codes should be reviewed before installation of equipment All equipment must be installe...

Page 5: ...8 BLOWER WHEEL 28 PLATE FINNED COIL CLEANING 29 CONDENSATE TRAP 29 GENERAL START UP INFORMATION 30 SPECIFIC EQUIPMENT DETAILS pages not numbered EQUIPMENT SPECIFICATION EQUIPMENT DRAWING SEQUENCE OF O...

Page 6: ...ondensation Also check for damage caused by rodents and be sure to eliminate any dust that may have built up on the components while the equipment was in storage LONG TERM STORAGE Please observe the f...

Page 7: ...otor sheave However some equipment may still utilize a variable pitch motor sheave on motors up to 30 Hp INDIRECT FIRED HEATING BURNER INFORMATION Titan Air Handlers can be equipped with inshot style...

Page 8: ...es Gas piping and exhaust venting must be sized and installed to comply with applicable codes and standards If in doubt regarding the application of the heater contact a sales representative or the fa...

Page 9: ...side of the equipment Review the equipment submittal drawing for the correct direction of the coil pull CURBING OUTDOOR MOUNTING The use of a full perimeter curb or mounting rails under the heater is...

Page 10: ...of the blower A properly designed duct transition from the blower outlet to a larger duct is recommended for long ducts or ducts with numerous elbows The equipment was designed for a specific CFM and...

Page 11: ...r coil piping is typically arranged to provide counterflow operation supply piping on lower air leaving side of coil and return on upper air entering side See Diagram on the right Verify that equipmen...

Page 12: ...itional sensor wiring may be required Carefully review the schematic and associated schematic symbol legend Note that legend may be on the parts legend sheet rather than on the schematic If an intake...

Page 13: ...g Options Recommended option for supporting accessories on a flat roof Other method of installation using sheet metal support legs IMPORTANT Not recommended for any unit larger than 125 model Typical...

Page 14: ...be found packaged in either a clear plastic bag or corrugated box NOTICE There may be more than one package of assembly materials provided 1 Apply provided caulk tape to the face of the joint to be bo...

Page 15: ...ed together caulk the external section seam s to provide a water tight seal IMPORTANT Check all external sheet metal seams for caulk shrinkage and re caulk if necessary Titan Air Inc does not warranty...

Page 16: ...washers Check all sections of the unit thoroughly for assembly hardware The assembly hardware will be found packaged in either a clear plastic bag or corrugated box NOTICE There may be more than one p...

Page 17: ...ction letter on the service side of the unit with the corresponding letter on the other section In addition also refer to the unit submittal drawing for proper assembly order 4 Lift blower section and...

Page 18: ...TANT Re caulk unit lifting lugs after assembly Check all external sheet metal seams for caulk shrinkage and re caulk if necessary Titan Air Inc does not warranty water damage equipment Unit seam seali...

Page 19: ...entry of snow rain and include an intake screen to meet ANSI standards Accessories on large equipment may be shipped in two pieces for field assembly As a result two damper actuators may need to be f...

Page 20: ...h the hood to the filter section except in step five substitute inch bolts in for self taping screws to attach the hood to the filter section 7 After all of the accessories are installed caulk each se...

Page 21: ...Titan Air highly recommends the discharge damper be mounted so the blades are orientated vertically If possible IMPORTANT Titan Air also highly recommends the discharge damper be mounted at the wall o...

Page 22: ...d diffuser is supplied by others Support diffuser at two points using field supplied materials See example below Square Tubing DISCHARGE DAMPER Secure turning vanes once adjusted in the field by other...

Page 23: ...t determine whether the drain pan is under negative or positive pressure DESIGN CONSIDERATION Calculate static pressure at the drain pan for worst case scenario Refer to the diagrams on the next page...

Page 24: ...1 inch wg B A 5 C A B Pipe Diameter inches Insulation if applicable POSITIVE PRESSURE P TRAP CALCULATIONS D Minimum 1 2 inch E 1 2 inch Maximum Total Static Pressure F D E Pipe Diameter inches Insulat...

Page 25: ...rocedure once per year FILTERS Dirty or clogged filters will restrict air flow which in turn affects the equipment performance Therefore it is necessary to check filters on a regular basis Several sta...

Page 26: ...alignment and belt tension are critical to belt and bearing service life Incorrect belt tension or misalignment of sheaves can cause any of the following Premature failure of bearings Premature failur...

Page 27: ...aves and then re tighten If a face width variation exists measure the difference between each side of the narrowest sheave and adjust until both sides are an equal distance from the straight edge BELT...

Page 28: ...ns of dirt or moisture lubrication may be required every 6 months to 1 year Refer to website for specific manufacturer cut sheets pertaining to motor bearing maintenance Typical motor bearing lubricat...

Page 29: ...ll also provide an initial check for pinholes or cracks that may not be visible Refrigerant leak detectors should be utilized for DX coils NOTICE Corrosion or deposits on copper or brazed joints may i...

Page 30: ...eration per the sequence of operation must be verified Apparent malfunction of a component may be caused by improper supply conditions field wiring errors or other problems unrelated to the component...

Reviews: