BC207 Series
Chapter 6: Operation Instructions
Page 107
MTN026962-D02
The
Normal Scan
pursues an ISO compliant measurements. The ISO standard requires that
"...
at least 10 measurements shall be taken. Approximately half of the measurements
shall be distributed within one Rayleigh Length on either side of the beam waist, and ap-
proximately half of them shall be distributed beyond two Rayleigh Lengths from the
beam waist
."
The first run of the Normal Scan is executed with respect to the entered number of
Data
Points
, in other words, like a coarse scan. A preliminary Rayleigh Length is calculated in order
to evaluate if the number of measured data points is sufficient to fulfill the ISO standard require-
ments. If so, a hyperbolic fit is applied. If not, a second run adds additional measurements
within the Rayleigh Length on both sides and/or beyond twice the Rayleigh Length.
For a M
2
measurement, running the Normal Scan is highly advised. The coarse scan is suitable
for a first estimate of the beam waist position or other preliminary measurements.
Reset
Restores the default settings for M² settings:
Parameter
Default Setting
Beam Width
Beam Width Clip (1/e²)
Wavelength
635 nm
Timeout
15 sec
Start
0 mm
Stop
200 mm
Min. Data Points
10
Scan Method
Normal Scan
Calculation Area
The settings for the
Calculation Area
can be made in the
. During a
Beam Quality Measurement (M
2
or Divergence), the Automatic Calculation Area is enabled by
default for effective noise reduction. Reflections and artifacts from filters, lenses or other optical
elements can be suppressed as well using the automatic Calculation Area.
This setting can be changed to manual, but this may affect the measurement.
By default the Clip Level of the Calculation Area is set to 1%. This is a reasonable value for
most applications and measurements. Lowering the clip level leads to increased calculation
area and noise level, this way increasing the measured the beam width.
For some cases it might be useful to adjust the Clip Level to cover the whole intensity.
40
Summary of Contents for BC207UV
Page 2: ...Copyright 2022 Thorlabs Version Date 8 1 10 Jan 2022 ...
Page 103: ...BC207 Series Chapter 6 Operation Instructions Rev 8 1 10 Jan 2022 Page 96 2022 Thorlabs ...
Page 133: ...BC207 Series Chapter 6 Operation Instructions Rev 8 1 10 Jan 2022 Page 126 2022 Thorlabs ...
Page 181: ...www thorlabs com ...