6
Commissioning
66
6.10
Installation of the components
It is absolutely essential to follow the notes in section 2
Safety and
disposal
when installing the Saveris components.
Do not install the Saveris base and the data loggers at their locations
until the measurement system is functioning as expected.
The Li-ion rechargeable batteries in the Saveris base and in the Saveris
Ethernet data loggers cannot be charged at sub-zero temperatures.
Avoid installation sites for these components with sub-zero
temperatures prevailing for extended periods of time.
After installation, perform another test run of the system; see section
6.11
Performing test run
.
6.10.1
Mounting the Saveris base on the wall
When selecting the location for the Saveris base, please take into
account that this must be positioned close enough to the computer
used and a possible power supply in accordance with the cabling
provided.
The mounting materials (screws, dowels, etc.) are not included in the
scope of delivery.
1
Position wall bracket at the required
location.
2
Using a pen, mark the locations for the fastening screws.
The distance between the fastening screws is 25 mm.
3
Prepare the fastening location for the attachment in accordance with
the material (e.g. drill hole, insert dowel).
4
Fasten wall bracket using appropriate screws.