October 2018
Service and Repair Manual
Boom Components
Part No. 1268557GT
Z®-135
/70
73
17 Use a soft metal drift to tap the pin halfway out
and lower one of the linkage arms down. Tap
the pin in the other direction and lower the
other linkage arm down.
Crushing hazard. The upper
primary boom lift cylinder linkage
arms could fall if not properly
supported when the pivot pins are
removed.
18 Attach a 5 ton / 5000 kg overhead crane to
both ends of the primary boom. Do not apply
any lifting pressure.
19 Remove the pin retaining fasteners from the
primary boom pivot pins.
20 Use a soft metal drift to remove the primary
boom pivot pins.
21 Carefully remove the primary boom from the
machine and place it on a structure capable of
supporting it.
Crushing hazard. The primary
boom could become unbalanced
and fall when removed from the
machine if not properly attached
to the overhead crane.
4-4
Primary Boom Lift Cylinder
The primary boom lift cylinder raises and lowers the
primary boom. The primary boom lift cylinder is
equipped with a counterbalance valve to prevent
movement in the event of a hydraulic line failure.
How to Remove the Primary
Boom Lift Cylinder
Bodily injury hazard. This
procedure requires specific repair
skills, lifting equipment and a
suitable workshop. Attempting
this procedure without these skills
and tools could result in death or
serious injury and significant
component damage. Dealer
service is strongly recommended.
Note: When removing a hose assembly or fitting,
the O-ring (if equipped) on the fitting and/or hose
end must be replaced. All connections must be
torqued to specification during installation. Refer to
Specifications,
Hydraulic Hose and Fitting Torque
Specifications.
Note: Perform this procedure with the boom in the
stowed position.
1
Remove the hose and cable clamps from the
primary boom lift cylinder.
2
Remove the cable track retaining fasteners at
the primary boom lift cylinder.
3
Place blocks under both ends of the primary
boom lift cylinder. Place another block under
the cylinder linkage arms under the primary
boom lift cylinder barrel-end pivot pin.
Summary of Contents for Genie Z-135/70
Page 14: ......
Page 37: ...October 2018 Service and Repair Manual Specifications Part No 1268557GT Z 135 70 23 T ...
Page 135: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 121 ...
Page 137: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 123 ...
Page 139: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 125 ...
Page 141: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 127 ...
Page 147: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 133 ...
Page 153: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 139 ...
Page 155: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 141 ...
Page 159: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 145 ...
Page 161: ...October 2018 Service and Repair Manual Manifolds Part No 1268557GT Z 135 70 147 ...
Page 233: ...October 2018 Service and Repair Manual 219 Generator Wiring Schematic ...
Page 236: ...Service and Repair Manual October 2018 222 Hydraulic Generator Welder Option ...
Page 242: ...Service and Repair Manual October 2018 228 Hydraulic Schematic from serial number 535 ...
Page 244: ......