L200Y SLIDING GATE OPERATOR USER
’S MANUAL
6
Conduit
In order to protect the wires, conduit must be preset into the concrete when it is poured. Wires
within the conduit shall be located or protected so that no damage can result from contact with
any rough or sharp part. If you have installed an external button switch, we advise you to use
two conduits: one for main power wire, another one for control wire. Always separate power
wires from control wires.
Concrete pad
The base unit of the gate operator requires a concrete pad in order to maintain proper stability.
The concrete pad should be approximately 400mm x 250mm x 200mm deep in order to provide
for adequate operation.
Anchors
You can use the anchor bolts, anchors, washers, and nuts. These anchors must be set into the
concrete when it is poured, or you can use wedge anchors.
Fig.5
Operator Base
Mount the gate operator base to the concrete pad.
Operator
Mount the gate operator to the base using nuts and washers. Verify that the operator is leveled
properly.
Installation of Rack (see Fig.6)
Fix the three nuts (in the same package with rack) on the rack element.
Lay the first piece of rack on the gear and weld the first nut on the gate.
Move the gate manually, checking if the rack is resting on the gear, and weld the second
and the third nut.
Bring another rack element near to the previous one. Move the gate manually and weld the
three nuts as the first rack, thus proceeding until the gate is fully covered.
When the rack has been installed, to ensure it meshes correctly with the gear.
The space between rack and gear is about 0.5mm.