14
www.tcsmeters.com
Total Control Systems
TCS 3000 Installation
Installation Procedure — Pump & Throttle
RED
BLACK
Installation Procedure:
1.
Locate the Pump Control (PMP. CRL) position on the terminal
board.
2.
Screw the cable gland into the back of the TCS 3000 register and
tighten into the housing.
3.
Run the Pump Control to the onboard computer or programma-
ble logic controller (PLC) wiring through the cable gland. Wire the
air eliminator float into the correct location on the terminal
board. Leave a small amount of slack on the wiring.
4.
Compress the cable gland on the TCS3000 register until it is snug
on the air eliminator float wiring.
The Pump Control is utilized as a positive output signal for the entire delivery pro-
cess. Providing security pump authorization and more accurate deliveries. Some-
times required to be used with onboard computer systems or programmable logic
controllers (PLC).
BLACK
RED
RED
BLACK
THROTTLE 1
THROTTLE 2
Installation Procedure:
1.
THROTTLE 1: Locate the Pump Starter (PMP START) port on ter-
minal for Throttle 1 positive output signal based on Flow Rate.
WARNING: Throttle 1 product selection will override the Additive
Injection parameter if selected.
2.
THROTTLE 2: Locate the Auxillary 1 (AUX 1) port on terminal for
Throttle 2 positive output signal based on Flow Rate.
3.
For both Throttle outputs, wire signal wire to (+) and ground to
(GND).
PUMP CONTROL