Inspection, Repair
286
Chapter 11
5.
Inspection, Repair
Before inspection, be sure to turn off the original power supply. Some circuits are still
applied voltage eve if the original power supply was turned off. Wait until these circuits
are completely out of voltage (4 minutes) and then start working.
Inspection point
Action
Inspection cycle
Attaching of each type of cover
Attach all the covers.
At start of working
Setting condition of embroidery
thread
Set it correctly.
Check breakage and/or bent of
needle.
Replace the needle.
Lubricating condition of each
section
Lubricate.
Automatic Lubrication System
Refill oil.
In the state of attachment
attached
Attach it correctly.
Belt tension (main shaft, X/Y
drive system)
Consult the distributor.
Once/3 months
Before repairing the machine, be sure to turn off the original power supply. Some circuits
are still applied voltage eve if the original power supply was turned off. Wait until these
circuits are completely out of voltage (4 minutes) and then start working.
If the machine needs the repair, the repair must be done only by the service personnel
assigned and trained by Tajima or qualified technician. (Consult your distributor.) Do not
change the specification nor modify the parts of the machine without due consultation
with Tajima. Such modification may have the risk against the operational safety.
When restarting the machine after repairs, attach all removed covers etc. as they were.
For the repair, use Tajima genuine parts for replacement.
!
WARNING
!
WARNING
!
CAUTION
RR05
Summary of Contents for TLMX Series
Page 23: ...Inspection before starting work 8 Chapter 1 ...
Page 59: ...Attachment 44 Chapter 2 ...
Page 113: ...Embroidery starts 98 Chapter 4 ...
Page 145: ...Operation and setting for embroidering 130 Chapter 5 2 Select the value 3 RR05 ...
Page 209: ...Other functions that must be remembered 194 Chapter 6 ...
Page 231: ...To resister frame position 216 Chapter 7 ...