MAINTENANCE PROGRAM
PILATUS PORTER PC6
CHAPTER 5
INSPECTION TIME LIMIT
DOCUMENT NO.:
SAP 27
Reissued: 2
Revision: 1
Date: July 2020
Page: 5 - 3
ITEM
MAINTENANCE REQUIREMENT
INTERVAL
Chapter 34 - Navigation
Pitot-Static System
Leak check
Drain
2 years
2 years
Standby Magnetic
Compass
Check swing
2 years
Encoding Altimeter System Functional test
Encoding calibration
IFR flight operations:
2 years
VFR flight operations:
On condition
Chapter 34 - Navigation
Altimeter
Functional test.
Barometer calibration.
IFR flight operations:
2 years
VFR flight operations:
On condition
Transponder System
Functional test
2 years
Chapter 35 - Oxygen
Regulator Panels (if
installed)
P/N 957.12.16.604
Overhaul
2 years or 2000 FH
Regulator Panels
(if installed)
P/N 957.12.16.106 and
957.12.16.201
Overhaul
5 years
Port Regulator (02D1 &
02D2 Pulse-Demand Unit) Send to service
2 years
Chapter 51 - Structures
Complete Structure -
Internal and External
Look for corrosion
1 year
Chapter 53 - Fuselage
Fuselage, Seat
Attachments and
Surrounding Structure
Examine
2 years
Stabilizer Trim Attachment
Components, FR12A
Examine (Ref. 53-30-00)
1100 flying hours or 12
months
(Whichever comes first,
Fuselage-Wing-Strut
Attachment-Brackets
Examine (Non Destructive
Inspection)
Fluorescent Dye Penetrant or Eddy
Current inspection.
(Ref. 53-28-00. Page Block 601)
3500 FH
or
7 years
(whichever comes first),
Fuselage Wing Fittings
Examine (Ref. 53-00-01. Page Block
601)
7000 FH
or
14 years
(whichever comes first),
Summary of Contents for PILATUS PORTER PC6
Page 2: ...MAINTENANCE PROGRAM PILATUS PC 6 DOCUMENT NUMBER SAP 27 REISSUE 2 REVISION 1 JULY 2020...
Page 3: ......
Page 4: ......
Page 97: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 7 of 26...
Page 98: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 8 of 26...
Page 99: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 9 of 26...
Page 100: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 10 of 26...
Page 101: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 11 of 26...
Page 102: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 12 of 26...
Page 103: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 13 of 26...
Page 104: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 14 of 26...
Page 105: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 15 of 26...
Page 106: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 16 of 26...
Page 107: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 17 of 26...
Page 108: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 18 of 26...
Page 109: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 19 of 26...
Page 110: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 20 of 26...
Page 111: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 21 of 26...
Page 112: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 22 of 26...
Page 113: ...Form ASI PC6 Engine Installation Reissued 2 Revision 1 Date July 2020 Page 23 of 26...
Page 122: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 6 of 25...
Page 123: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 7 of 25...
Page 124: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 8 of 25...
Page 125: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 9 of 25...
Page 126: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 10 of 25...
Page 127: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 11 of 25...
Page 128: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 12 of 25...
Page 129: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 13 of 25...
Page 130: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 14 of 25...
Page 131: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 15 of 25...
Page 132: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 16 of 25...
Page 133: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 17 of 25...
Page 134: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 18 of 25...
Page 135: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 19 of 25...
Page 136: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 20 of 25...
Page 137: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 21 of 25...
Page 138: ...Form ASI PC6 Engine Removal Reissued 2 Revision 1 Date July 2020 Page 22 of 25...
Page 144: ...Form ASI PC6 Propeller Installation Reissued 2 Revision 1 Date July 2020 Page 3 of 7...
Page 145: ...Form ASI PC6 Propeller Installation Reissued 2 Revision 1 Date July 2020 Page 4 of 7...
Page 151: ...Form ASI PC6 Propeller Removal Reissued 2 Revision 0 Date October 2019 Page 3 of 7...
Page 152: ...Form ASI PC6 Propeller Removal Reissued 2 Revision 0 Date October 2019 Page 4 of 7...
Page 231: ...Form No ASI MD 71 Revision 3 July 2020 Page 2 of 4 FIGURE 1...
Page 232: ...Form No ASI MD 71 Revision 3 July 2020 Page 3 of 4 FIGURE 2...
Page 233: ...Form No ASI MD 71 Revision 3 July 2020 Page 4 of 4 FIGURE 3...
Page 244: ...Form No ASI MD 90 Revision 3 July 2020 Page 4 of 8...
Page 246: ...Form No ASI MD 90 Revision 3 July 2020 Page 6 of 8...