CheckPoint Pharma and CheckPoint
e
Operation and Maintenance Manual
SUEZ © 2018
52 of 112
DLM 97200-03 EN Rev. A
Figure 9: Connecting the Power Wiring (With Conduit)
15. Connect the ground wires to the ground stud; the wire from the power inlet should be on the
Stacking Order for the Ground Wires).
A connector for 16-14 AWG wire is provided in the CheckPoint Accessories Kit. If you use wire of
a different gauge, you must provide an appropriate connector.
From
power in
From
power filter
Figure 10: Stacking Order for the Ground Wires
16.
If you also are using conduit for I/O cabling, do not replace the Sensor’s covers. Proceed to the
next step.
If you are installing I/O cabling but are not using I/O conduit, replace the Sensor’s covers and
proceed to the next step.
If you are not using the optional I/O kit, proceed to