Commissioning/Decommissioning
08|2020 EN
41
6 Commissioning/Decommissioning
6.1 Commissioning
NOTICE
Damage to the drive (sliding bearing) due to dry running and
overheating!
Make sure that the system is always operated 350 mm from
the system centre under water.
After longer periods at standstill, the drive unit must be checked
for smooth action in the off and voltage-free state.
6.1.1 Switching on the system
WARNING
Danger of sucking in with wrong rotation direction! The water
current must move from the middle outflow nozzle (42) towards
the centre of the pool!
No persons may be directly in front of the outflow nozzle!
In case of incorrect rotation direction, switch off the system
immediately and check the connections of the motor or the
orange cable (check wire labelling) according to the circuit
diagram specifications and connect correctly.
The motor can be switched on by the preceding frequency
converter (61) directly on the operating panel (55) at the piezo
buttons (64) in the pool or with the remote control unit (66).
6.2 Operation
6.2.1 Switching
on/off
The system can be switched on and off with the remote control
unit (66) or by pressing the middle piezo button (64) installed in
the panel.
The button lights “blue” in the off state and “red” in the on state.
The turbine starts up with a delay of approx. 3 seconds when
switching on.
A medium volume flow of 1200 rpm is set here (basic setting).
Summary of Contents for BADU BADUJET Turbo Pro
Page 1: ...EN EN Translation of original operation manual Submerged counter swim unit ...
Page 20: ...Installation 20 EN 08 2020 Pool cutout for concrete pools formwork Fig 4 ...
Page 21: ...Installation 08 2020 EN 21 Installation of formwork for concrete pools Fig 5 ...
Page 34: ...Installation 34 EN 08 2020 5 4 4 Control cable wiring diagram Fig 18 ...
Page 49: ...Technical Data 08 2020 EN 49 10 2 Exploded drawing Fig 26 ...