8  Troubleshooting

disturbance

reason

correction

No internet connection (the storage 
system is not displayed at the Internet 
portal https://meine.sonnenbatterie.de)

No connection between the storage system 
and the server.

► 

Make sure that the Ethernet line between 

the storage system and the Router of the home 
network is correctly connected.

► 

Make sure that the Router of the home 

network allows connections on the following 
ports:

TCP-Port

Service

22

SecureShell (ssh)

37

Time Server (ntp)

80

Online-Check (http)

222

VPN (Serververbindung ssl)

232

VPN (backup)

443

App-Steuerung (https)

UDP-Port

Service

1196

(Serververbindung, ssl)

 

KD-291 | Part no. 52187 | EN | X01

page 59 of 63

Heruntergeladen von

 

manualslib.de

 

Handbücher-Suchmachiene

 

Summary of Contents for sonnenBatterie eco 8.0

Page 1: ...933 444 info sonnenbatterie de www sonnenbatterie de Installation instructions sonnenBatterie eco 8 0 for authorised electricians KD 291 Part no 52205 X01 Heruntergeladen von manualslib de Handb cher...

Page 2: ...y hotline 49 0 83 049 2933 444 Email info sonnenbatterie de Document Document number KD 291 Item number 52205 Version X01 Publication date 27 09 2016 Scope of validity This document relates to the fol...

Page 3: ...rnings 9 3 Product description 12 3 1 Technical data 12 3 2 System components 13 3 3 Type plate 14 4 Transport and storage 15 4 1 Storage 15 4 1 1 Ambient conditions during storage 15 4 1 2 Storing th...

Page 4: ...t 39 6 6 Using accessories 40 6 6 1 Using heat pump control 40 6 7 Installing the battery modules 43 6 7 1 Measuring the battery module voltages 44 6 7 2 Numbering the battery modules 44 6 7 3 Definin...

Page 5: ...g connection to storage system 57 7 3 2 Running the commissioning wizard 58 8 Troubleshooting 59 9 Decommissioning 60 10 Uninstallation and disposal 61 10 1 Uninstallation 61 10 2 Disposal 61 11 Commi...

Page 6: ...this document sonnenBatterie eco 8 0 storage system 1 3 Explanation of symbols Extremely dangerous situation leading to certain death or serious injury if the safety information is not observed Danger...

Page 7: ...d electricians Authorised electricians must meet the following criteria The company for which the electrician works must be certified by sonnen GmbH The electrician must be considered competent and re...

Page 8: ...he event of a fire in the vicinity of the product or in the storage system itself proceed as follows Only firefighters with appropriate protective equipment safety gloves safety clothing face guard br...

Page 9: ...haustive The authorised electrician is responsible for knowing and observing all of the regulations relevant to their work 2 5 Warnings This section contains specific warnings that must always be obse...

Page 10: ...attery module is deactivated when the fuse connector is unplugged No voltage runs between the plus and minus contacts of the battery module If all interconnected battery modules are deactivated it is...

Page 11: ...tery modules Do not allow the battery modules to come into contact with water except when extinguishing a fire in the storage system Do not heat the battery modules Operate them only within the permis...

Page 12: ...p to 16 kWh Dimensions H B T in cm 70 64 22 184 64 22 184 64 22 184 64 22 184 64 22 184 64 22 184 64 22 184 64 22 Weight in kg 53 93 120 147 174 201 228 255 Power meter Voltage measurement inputs Nomi...

Page 13: ...er pad F1 fuse switch On off switch for storage system XAC Mains connection socket Sending and receipt of digital signals XDI Digital inputs Interface to receive digital signals XDO Digital outputs In...

Page 14: ...ollowing information is specified on the type plate Item designation Item number Version hardware version Technical data of the storage system The nominal power and battery capacity of the storage sys...

Page 15: ...modules for no longer than 6 months Install the battery modules in the storage system after 6 months at the most and commission the storage system During storage the orange fuse plug must not be plugg...

Page 16: ...amaged storage system under any circumstance Paragraph 425 of the German Commercial Code Handelsgesetzbuch forms the legal basis for processing transport damage The shipping company can only be held l...

Page 17: ...sible Unpack the goods Inspect the goods for hidden not immediately visible transport damage If transport damage is discovered Stop unpacking the product Collect photographic evidence of the damage Re...

Page 18: ...em for condensation before installation Only install the storage system if there is no condensation on the surfaces If the storage system has been transported in sub zero temperatures proceed as follo...

Page 19: ...Voltage Metering Spannungsmessung 21512 1x 1x 1x 1x 45300 45310 45320 45303 45313 45323 1x 11384 11423 1x 30536 10562 10044 4x 2x 11123 2x 21515 10044 Self lockung nur 21545 Pedestal color silver 105...

Page 20: ...mum distances to neighbouring objects The minimum distances ensure that there is sufficient heat dissipation the storage system door can be opened easily and there is sufficient space for maintenance...

Page 21: ...ng the filter plates Figure 7 Removing the filter plates 2 1 1 The filter plates of the main and optional extension cabinet can be removed Removing them makes it easier to install the battery modules...

Page 22: ...The screw head must not exeed 5 mm 5 6 2 Placing the levelling mat or the pedestal The levelling mat 1 is part of the scope of delivery for the extension cabinet It is used to compensate uneven floors...

Page 23: ...mat or the pedestal C With big extension cabinet up to 16 kWh Figure 12 Drill template for storage systems with big extension cabinet figure is not to scale all specifications are in millimetres A Ma...

Page 24: ...ew head and wall 2 mm Apply suitable screws and anchors see 5 6 1 pg 22 to the previously drilled holes The screw should not be completely screwed in The screw head should protrude from the wall by ap...

Page 25: ...rews 6 Connect the housing Figure 18 Connecting the housing An earth conductor is already connected in the extension cabinet Connect the other end of the earth conductor to the earth bolt in the main...

Page 26: ...ger to life due to electrocution Install residual current devices RCDs upstream of the storage system The rated differential current of the residual current device RCD must be 30 mA The type of RCD us...

Page 27: ...components The miniature circuit breaker 1 protects the connection line to the storage system The power meter 2 and the transformer interfaces 3 are used to measure the consumption and generation of p...

Page 28: ...n L2 10 Public electrical mains 16 Current transformer for production L2 5 Current transformer for consumption L3 11 B6 miniature circuit breaker 17 Current transformer for production L3 6 Storage sys...

Page 29: ...ed by the supplied miniature circuit breakers B6 The supplied miniature circuit breakers do not have to be installed if the lines are already protected by existing circuit breakers Figure 22 Correct l...

Page 30: ...orks if the current and voltage of the same phase are measured Example clamp on current transformer L1 marked with number 1 must be connected to phase L1 This phase L1 must also be connected to termin...

Page 31: ...the router of the home network 3 Figure 25 Connecting the Ethernet line to the top of the main cabinet 1 Angled connector 2 Patch cable not included in scope of delivery 3 Home network router XETH Eth...

Page 32: ...onnect the patch cable 1 as shown in the following figure Figure 26 Connecting the Modbus line 1 Angled male connector 2 Patch cable not included in scope of delivery 3 Power meter 4 Modbus terminal s...

Page 33: ...the power supply Only authorised electricians are permitted to carry out electrical work Connect the AC line as shown in the figure below Ensure that the stickers 2 and 3 face upwards Close the lock...

Page 34: ...lectricians are permitted to carry out electrical work The wiring configurations described in this section are examples only and serve as a guide for electricians working on the system The wiring conf...

Page 35: ...n we recommend installing multiple terminals which are connected via a bridge 4 to the earth GND 1 Signal line 2 Signal line 3 Terminal strip 4 Bridge for connecting terminals XDO Digital outputs Wire...

Page 36: ...72 2 3 4 Level K71 K72 0 1 2 3 Tabelle 5 Make contact positions of K71 and K72 relays depending on activated level Function Relays K71 and K72 are connected to the green PV reduction 1 and yellow PV r...

Page 37: ...eduction digital outputs as shown in Figure 31 pg 36 Set the following values on the PV inverter Level Max active power 0 100 1 Feed in limit of PV system in 2 Half of feed in limit of PV system in 3...

Page 38: ...e self consumption switch can be configured using the commissioning wizard see section 7 3 pg 56 Adjust the switch on threshold and minimum switch on duration to suit the consumers that are activated...

Page 39: ...max SoC digital output can be configured using the commissioning wizard see section 7 3 pg 56 Set suitable values for the min SoC and max SoC variables Application example Figure 35 Activating deacti...

Page 40: ...obtained before the heat pump control is installed in the electrical distributor The heat pump control can be used when the heat pump is billed using a separate energy meter In this case the heat pum...

Page 41: ...lf consumption switch is deactivated Then Q31 de energises The heat pump current path is closed Wiring the heat pump control Wire the heat pump control as shown in Figure 36 pg 42 Ensure that a de ene...

Page 42: ...ansformer interface for consumption 14 Bidirectional counter 5 Heat pump 10 Residual current device required in TT network 15 Heat pump energy meter page 42 of 63 KD 291 Part no 52187 EN X01 5s 1 AV A...

Page 43: ...s of the battery module If all interconnected battery modules are deactivated it is safe to work on a battery module When working on the DC circuit Set aside metal jewellery Switch off the storage sys...

Page 44: ...greater than 1 V Notify the service team Figure 37 Measuring the battery module voltages V COM V 6 7 2 Numbering the battery modules Figure 38 Numbering the battery module 0 Apply the supplied sticker...

Page 45: ...battery modules without extension cabinet left and with extension cabinet right 0 0 1 2 3 4 5 6 7 If no extension cabinet is used Position the battery module as shown in the left part of the image If...

Page 46: ...lines are allowed to be plugged into red sockets Only black lines are allowed to be plugged into black sockets Figure 42 Correctly connected top and incorrectly connected bottom DC line Ensure that a...

Page 47: ...Connect the DC lines as shown in the figure on the right KD 291 Part no 52187 EN X01 page 47 of 63 0 F1 X1 Figure 43 Connecting the DC lines on the sonnenBatterie eco 8 2 without extension cabinet He...

Page 48: ...ole of the last battery module with the highest number With a sonnenBatterie eco 8 2 this is battery module 0 with a sonnenBatterie eco 8 4 this is battery module 1 with a sonnenBatterie eco 8 6 this...

Page 49: ...MS lines as shown in the following figures Use the supplied BMS communication lines Figure 45 Connecting the BMS communication line on the sonnenBatterie eco 8 2 0 Combox ON 1 2 3 4 KD 291 Part no 521...

Page 50: ...communication lines to 8 battery modules 0 1 2 3 4 5 6 Combox 7 ON 1 2 3 4 0 ON 1 2 3 4 0 ON 1 2 3 4 0 ON 1 2 3 4 ON 1 2 3 4 0 ON 1 2 3 4 0 ON 1 2 3 4 0 page 50 of 63 KD 291 Part no 52187 EN X01 Herun...

Page 51: ...9 Entering the battery capacity nominal power on the type plate Tools Permanent marker Mark off the correct battery capacity and nominal power on the type plate of the storage system The type plate i...

Page 52: ...er plates 1 Mount the filter plate at the extension cabinet 2 Slide the filter plate down till it is in its end position 3 Mount the filter plate at the main cabinet 4 Slide the filter plate down till...

Page 53: ...arth bolt 3 Take care of the positioning of the components 4 to 8 Tighten the locking nut 8 with a torque of 5 Nm 6 8 3 Mounting cover Figure 50 Mounting the cover of the extension cabinet Hook the co...

Page 54: ...AC supply is correctly connected The AC line meets the requirements of all local and national guidelines for line dimensions The dimensions of the miniature circuit breaker installed in the AC line a...

Page 55: ...kwise Remove the cover 2 7 2 2 Switching on the storage system Abbildung 52 Fuse switch F1 and switch S1 at the top side of the storage system 1 Press switch S1 and hold it down while the following st...

Page 56: ...igured The operator as well as the authorised electrician have to enter some informations while the commissioning wizard is running The storage system is only ready for operation if the commissioning...

Page 57: ...m 4 3 XETH 1 2 Start a browser e g Firefox Chrome Safari at your laptop Enter the adress finde meine sonnenbatterie de in the adress line of your browser https finde meine sonnenbatterie de The follow...

Page 58: ...box 3 Click the button 4 to confirm your entries Figure 55 login page 1 Language selection list 2 User selection list 3 Password entry box 4 Confirm button User Password EN DE User Installer Service V...

Page 59: ...ine between the storage system and the Router of the home network is correctly connected Make sure that the Router of the home network allows connections on the following ports TCP Port Service 22 Sec...

Page 60: ...d Do not disconnect the storage system from the public electrical mains for an extended period of time Figure 56 Fuse switch F1 and switch S1 on top of the storage system of of S1 F1 Remove the cover...

Page 61: ...ed from sonnen GmbH Never transport damaged battery modules Figure 57 WEEE symbol The storage system and the batteries it contains must not be disposed of as domestic waste Dispose of the storage syst...

Page 62: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried t 49 0 8304 92933 444 o info sonnenbatterie de Heruntergeladen von manualslib de Handb cher Suchmachiene...

Page 63: ...Details on electrician carrying out the work Name Company Certification number Details on network topology mark off the applicable network TT TN S TN C S TN C TN C classic earthing Details on PV syst...

Reviews: