2.3.2 Rack Installation
1. Install the cage nuts on the corresponding positions in the rack, as shown in
Figure 18
�
a. Install cage nuts in the two lower square holes of 1U space and in the two upper square holes of 2U space of all
four rack posts� These cage nuts will secure the optional shelf that will support the weight of the SolaHD S5KC�
b. Install a cage nut in the middle square hole of 4U, 6U, 10U, 12U spaces, respectively, again in all four posts� The
cage nuts will help secure the UPS in the rack�
Figure 18: Install cage nuts
2. Install the rack-mount shelf on the corresponding position between 1U space and 2U space on the bottom of the
rack, as shown in
Figure 19
�
Figure 19: Install the tray
3. Install the guide rails (ramp) in the mounting slot at the front of the tray, as shown in
Figure 20
�
Detail A
Floating Nut
Detail A
Floating Nut
A
Detail B
Screw,16 places
Detail B
Screw
(16 places)
Tray
B
B
18 | 2�0
INSTALLATION
Phone: 800.894.0412 - Fax: 888.723.4773 - Web: www.clrwtr.com - Email: [email protected]