ALC404 LIGHTING TOWER CONTROLLER USER MANUAL
ALC404 Lighting Tower Controller 2018-11-06 Version 1.1 Page 67 of 83
battery damaged and cannot been full charged, controller will force the unit to stop after the pre-set
maximum
Under Voltage Charging Time
to prevent accidents.
The work mode can be set as Invalid, Auto Mode Active, Manual Mode Active, Auto And Manual Mode
Active.
7.15
TIMER MODE SELECT
Timer start mode can be set as daily, weekly, monthly and custom daily start time in one week. Users
can set the start time, run duration, detailed one day to start for each month / week, or custom weekday start
or not start functions. If the run duration is set as 00:00, then the unit will not be started.
7.16
SUNRISE/SUNSET SETTING
Users can select corresponding city or define city’s information (longitude, latitude and time zone) via PC
software Sunrise/set settings and click Sunrise/set Massage to download the information into controller;
then controller will run in auto sunrise/sunset mode.
NOTE
:
The information can be configured by software via PC only.
7.17
LOW FUEL LEVEL REDUCE LIGHT NUMBER (INVALID WHILE MAINS SUPPLY POWER)
Choose Low Fuel Level Light-off settings of Load Settings page to reduce the number of lights along
with the lowering of fuel level to reduce fuel consumption. If this function is enabled and fuel level associated
with the sensor, lights number can be reduced automatically through adjusting parameters of Low Fuel
Level Light-off settings.
7.18
REALIZE MAINS SUPPLY POWER VIA EXTERNAL DIGITAL INPUT PORT
This function allows external connected mains to supply power for the unit. If mains are active, whatever
working mode the unit states, genset will stop (genset not in standby status) and not allowed to start. At the
moment, mains active/reactive/apparent power and power factor are calculated by the controller (total
energy/start time, and current energy/start time are not calculate), meanwhile, controller overall controls the
light based on the mains status.
Controller uses the same port as the generator sampling voltage to sampling mains voltage. If use this
function, mains/generator switch function must be controller external of the controller. When the input port
that configured as 59 Mains Supply Active is active, controller will judge the detecting voltage is mains
supply.
When mains supply is active, engine shuts down, but the light controlled still keep the previous status.
When mains supply is active, controller can only control the lights on the lighthouse on and off, but not
control the genset start up.
When mains supply is abnormal, controller enters into mains abnormal delay, and all lights are turned off
after the delay. When mains supply is normal, all lights are turned on again.