7 COMMISSIONING
7.1
Preliminary operations
a
WARNING
– Should it be necessary to access the areas in the
bottom part of the appliance, make sure that the
system components and pipes are not hot (risk of
burning).
– Before replenishing the heating system, put on
protective gloves.
Before commissioning the appliance, check that:
– the type of gas is correct for the appliance
– the gas isolation valves for the heating system and the wa-
ter system are open
– the siphon has been filled.
7.2
Before commissioning
After having carried out the preliminary operations, proceed
as follows:
– set the main system switch to "ON"
ON
Fig. 46
– the type of gas for which the boiler has been calibrated,
"nG"
(methane) or
"LG"
(LPG,) will appear followed by the power.
Finally
"- -"
will appear on the display
– check that the system pressure as shown when the system
is cold , is between
1 and 1.2 bar
– press the
y
button twice to select “WINTER mode”
n
.
The value of the delivery sensor detected at that moment
will appear on the display
7.3
Parameter setting and display
To go into the parameter menu:
– from the selected mode (eg. WINTER)
– turn dials
t
and
r
to the maximum
– simultaneously press the
>
and
<
buttons (~ 5 s) until
“PAR
01”
(parameter number) appears on the display along with
the set value (0÷12) (consult the table in the “Circuit Board
Replacement” paragraph)
– press the button
>
to scroll up the list of parameters and
then
<
to scroll down the list
NOTE:
holding the buttons
>
or
<
increases the speed of the
scrolling movement.
– once the required parameter has been reached, press the
button
y
for approximately 3 seconds to confirm and
access the set value which will then flash and can then be
modified
– to modify the value in the permitted range, press the but-
tons
>
to increase it or
<
to decrease it
– once the required value has been reached, press the button
y
to confirm.
Once all the desired parameter values have been modified,
simultaneously
press, for ~ 5 s, the
>
and
<
buttons to exit the
parameters menu, until the home page reappears.
Summary of Contents for 8116910
Page 4: ...4 ...
Page 14: ...14 ...
Page 54: ...54 9 EXPLODED VIEWS Frame ...
Page 55: ...55 Hydraulic assembly ...
Page 56: ...56 Exchanger Combustion ...
Page 57: ...57 Control panel ...
Page 58: ...58 Gas valve Air gas duct Fan ...
Page 79: ...79 ...