![Silicon Graphics Prism User Manual Download Page 220](http://html.mh-extra.com/html/silicon-graphics/prism/prism_user-manual_1271592220.webp)
198
007-4701-003
C: Installing Rack Systems
Pre-Installation Activities
Perform the following pre-installation activities:
•
Perform site verifications (see “Site Plan Verification” on page 198)
•
Gather appropriate tools to complete the installation (see “Tools Required” on page 198)
•
Ensure that the correct power receptacle is installed and properly wired (see “Power
Receptacle Verification” on page 199)
Note: You can perform the pre-installation activities days or weeks before you receive your
system.
Site Plan Verification
Ensure that all site requirements are met before your system arrives. If you have questions about
the site requirements or you would like to order full-size floor templates for your site, contact a
site planning representative by e-mail ([email protected]) or by telephone (+1 715 726 2820).
Tools Required
Table C-1 lists the tools that you need in order to complete the installation.
Table C-1
Installation Tools
Tool
Part Number Purpose
13-mm wrench
7260744
Adjust the leveling pads.
13-mm socket (3/8-in. drive)
7260726
Remove bracket bolts from tall rack shipping crate.
19-mm socket (3/8-in. drive)
9470618
Remove bolts from short rack shipping crate.
Extension, 6-in. (3/8-in. drive)
7260655
Used with ratchet and sockets.
Ratchet, reversible (3/8-in. drive)
7260755
Used with extension and sockets.
Level, 9-in.
9470556
Level the rack.